海南东环铁路全风化花岗岩路基填料改良试验 |
| |
引用本文: | 刘祖富.海南东环铁路全风化花岗岩路基填料改良试验[J].路基工程,2010,0(3):157-158. |
| |
作者姓名: | 刘祖富 |
| |
作者单位: | 中铁二院工程集团有限责任公司工程测试中心,成都610031 |
| |
摘 要: | 海南东环铁路A,B组填料稀缺,设计填料利用路堑挖方和隧道弃方为主,但其料源60 %以上为全风化花岗岩C,D组,需进行改良才能满足工程要求。结合勘察设计,全线选取了有代表性的10组D类填料和10组C类填料进行改良研究,提出了最佳改良方案:高液限的全风化花岗岩用石灰改良,掺量为9 %;低液限全风化花岗岩用水泥改良,掺量为5 %。试验结果为设计和施工提供了依据,解决了海南东环线A,B组路基填料稀缺的重大工程问题。
|
关 键 词: | 全风化花岗岩 路基填料 改良试验 |
收稿时间: | 2019-11-11 |
Improvement Test of Decomposed Granite Foundation Filling in Hainan East Ring Railway |
| |
Authors: | LIU Zu-fu |
| |
Affiliation: | LIU Zu-fu (Engineering Test Center of China Railway Eryuan Engineering Group Co.,Ltd.,Chengdu 610031,China) |
| |
Abstract: | Hainan East Ring Railway lacks of A and B class filling material.Design fillings are mainly from excavation and tunnel discard,but above 60 % is C,D class decomposed granite,which shall be improved to satisfy engineering requirement.Combined with investigation design,10 groups of D-class filling and 10 groups of C-class filling are conducted improvement test for the whole line,and the best improvement program is put forward.Decomposed granite with high hydraulic limit shall be improved with lime,with mixing proportion of 9 % and that with low hydraulic limit shall be improved with cement,with mixing proportion of 5 %.The test result can be reference for design and construction and has settled the major engineering problem of A,B class foundation fillings scarcity for Hainan East Ring Railway. |
| |
Keywords: | decomposed granite foundation fillings improvement test |
本文献已被 维普 万方数据 等数据库收录! |
| 点击此处可从《路基工程》浏览原始摘要信息 |
|
点击此处可从《路基工程》下载全文 |
|