成都地铁1号线盾构区间穿越停车场出入线施工技术研究
引用本文:林强.成都地铁1号线盾构区间穿越停车场出入线施工技术研究[J].路基工程,2018,0(3):214-218.
作者姓名:林强
作者单位:中铁二局工程有限公司城通分公司, 成都 610000
摘    要:以成都地铁1号线三期首期工程穿越东寺停车场出入场线为依托,从前期施工的加固措施、施工控制措施以及施工监测措施进行了有益尝试并取得了较好的效果,形成了一套对于地铁盾构区间穿越停车场出入线施工技术,施工验证其累计沉降位移均处在安全的位移范围。

关 键 词:盾构隧道    卵石地层    下穿停车场    施工措施    掘进参数
收稿时间:2019-11-06

Study on Construction Technology of Chengdu Metro Line1 Shield Interval passing through Parking Lot Access Line
Abstract:Because buildings are dense in cities, the development and utilization of urban underground space will inevitably have an impact on the projects already built on the ground, so that the surrounding environment of the already-built projects will be changed and even unpredictable risks may even occur. With the first phase of Phase Ⅲ of Chengdu Metro Line 1 passing through Dongsi parking lot access line as an example, some beneficial attempts were made in this paper from the aspects of reinforcement measures at early stage, construction control measures and construction monitoring measures. Also, a set of construction technology of metro shield interval passing through the parking lot access line was formed and it was verified during the construction that the cumulative settlement displacement is within the safe range of displacement.
Keywords: