跨既有铁路单孔128m竖曲线箱梁顶推施工技术
引用本文:李小和.跨既有铁路单孔128m竖曲线箱梁顶推施工技术[J].铁道建筑技术,2012(8):8-12.
作者姓名:李小和
作者单位:中国中铁六局集团有限公司,北京,100036
摘    要:竖曲线混凝土梁顶推施工很少见,北京市通顺路改建工程跨越京承铁路设计采用单孔128 m系杆拱,位于R2 300 m的竖曲线上。结合该桥的施工实践,介绍了单孔128 m竖曲线箱梁顶推施工技术特点和关键施工技术。

关 键 词:跨既有铁路  竖曲线箱梁  顶推  施工

Jacking Construction Technology of Single Hole 128 m Vertical Curve Box Beam across Existing Railway
Li Xiaohe.Jacking Construction Technology of Single Hole 128 m Vertical Curve Box Beam across Existing Railway[J].Railway Construction Technology,2012(8):8-12.
Authors:Li Xiaohe
Institution:Li Xiaohe ( China Railway 6th Group Bureau Co. Ltd. , Beijing 100036, China)
Abstract:Vertical curve concrete girder is rarely seen, Tongshun Road reconstruction work in Beijing across Beijing-Chengde Railway design uses a 128 m single hole tied arch located in the R2 300 m vertical curve. Combined with the bridge's construction practice, the paper introduces the characteristics and key construction technology of the single hole 128 m vertical curve box beam jacking construction technology.
Keywords:across existing railway  curve box girder  jacking  construction