砂井联合超载预压控制软土地基路基工后沉降的优化设计
引用本文:王炳龙,宫全美,周顺华,杨红伟.砂井联合超载预压控制软土地基路基工后沉降的优化设计[J].铁道学报,2004,26(6):75-80.
作者姓名:王炳龙  宫全美  周顺华  杨红伟
作者单位:同济大学,道路与交通工程教育部重点实验室,上海,200331
基金项目:道路与铁道工程国家重点学科资助
摘    要:以经济效益为目标函数,软土地基路基工后沉降、沉降速率双控制指标为约束条件,建立了砂井联合超载预压处理软土地基的优化设计模型。通过一实例,采用遗传算法对控制工后沉降的3个主要设计参数:砂井间距、超载量和预压时间进行了优化求解。按优化的参数结果表明,通常情况下铺轨时加固区主固结沉降已完成,地基的工后主固结沉降大小主要取决于砂井底部的受压土层,控制的主要参数为超载量和预压时间,同时表明了作者所采用方法的有效性。

关 键 词:砂井联合超载预压  软土地基  工后沉降  遗传算法  优化设计
文章编号:1001-8360(2004)06-0075-06
修稿时间:2004年4月14日

Optimizaton Design for Surcharge Precompression on Ground with Sand Drains to Control the Post-constrution of Subgrade over Soft Soils
WANG Bing-long,GONG Quan-mei,ZHOU Shun-hua,YANG Hong-wei n,Tongji University,Shanghai ,China.Optimizaton Design for Surcharge Precompression on Ground with Sand Drains to Control the Post-constrution of Subgrade over Soft Soils[J].Journal of the China railway Society,2004,26(6):75-80.
Authors:WANG Bing-long  GONG Quan-mei  ZHOU Shun-hua  YANG Hong-wei n  Tongji University  Shanghai  China
Institution:WANG Bing-long,GONG Quan-mei,ZHOU Shun-hua,YANG Hong-wei n,Tongji University,Shanghai 200331,China)
Abstract:The mathematical model of surcharge precompression on ground with sand drains is established for optimization design. In this model, economic utility is the object function; the post-construction settlement and the rate of settlement of soft subsoil are constraint conditions. A calculating program that solves the optimum values of controlling post-construction settlement is written by Genetic Algorithm. As an example, the program solves the values which include the sand drain spacing,the level of surcharge and the time of preloading. The results show: The primary consolidate settlement of the improvement zone has usually completed before the rails are installed; the quantity of primary consolidate settlement of post construction depends on the compressed strata below soft soil; the key design parameters which control the post-construction settlement are the level of surcharge and time of preloading. The model in this paper is effective to control the post- construction of the subgrade over soft soils.
Keywords:surcharge precompression on ground with sand drains  soft soil ground  post-construction settlement  Genetic Algorithm  optimization design