升降折叠工程列车在长大既有线隧道整治中的应用
引用本文:张文卷.升降折叠工程列车在长大既有线隧道整治中的应用[J].国防交通工程与技术,2014(6):72-74.
作者姓名:张文卷
作者单位:中铁十八局集团第二工程有限公司,河北 唐山,064000
摘    要:电气化改造前需要对既有铁路线上的隧道进行病害整治,病害整治施工时必须按照既有线施工规定,在“天窗”时间点内作业。为充分利用有限“天窗”时间,在京九铁路隧道整治中研发了可升降折叠作业的工程列车,在8个月的时间内完成了全部96座单双线隧道病害整治。每列工程列车由内燃机车、多台铁路轨道平板车组成,将隧道病害整治所需要的施工设备结合施工时的作业空间全部合理地配置在列车上;工程列车的作业平台分为两层,可升降、可折叠,在上面可以进行隧道钻孔、注浆、砂浆搅拌、混凝土搅拌、喷射混凝土等作业。实践证明,使用升降折叠工程列车进行隧道病害整治可提高工作效率、降低劳动强度,值得进一步推广使用。

关 键 词:既有线隧道  病害整治  工程列车  作业平台  升降  折叠

On the Application of the Hoistable Folding Engineering Trains to the Repair of Long and Large Tunnels of the Existing Railways
Zhang Wenj uan.On the Application of the Hoistable Folding Engineering Trains to the Repair of Long and Large Tunnels of the Existing Railways[J].Traffic Engineering and Technology for National Defence,2014(6):72-74.
Authors:Zhang Wenj uan
Institution:Zhang Wenjuan (The 2nd Engineering Co. Ltd. of the 18th Bureau Group of China Railway,Tangshan 064000,China)
Abstract:All the defects or damaged parts of the tunnels of the existing railways have to be overcomed or repaired before they are electrically transformed.In the course of the repair work,all the repair operations have to be performed during the so-called“scuttle periods”according to the construction requirements for the existing railways.To make full use of the limited“scuttle periods”,a hoistable folding engineering train was developed during the repair construction of the tunnels of the Jing-Jiu Railway.With the help of the newly-developed engineering train,the total 9 6 single-line or double-line tunnels were successfully repaired within 8 months.Every engineering train is made up of an internal combustion locomotive and several railway track flat wagons,where all the construction equipment and devices needed for the repair work are rationally provided,and the work clearance is fully considered.The engineering train has two stories of working platforms,which are both hoistable and foldable and on which hole-boring for the tunnel,slip-casting,mortar mixing,concrete mixing,concrete-jetting,and other processes may all be performed.Practice shows that the application of the hoistable folding engineering train to the repair work of tunnels helps improve work efficiency and lower the laboring strength,and therefore,is worth further popularizing.
Keywords:tunnels of existing railways  control and repair of defective or damaged proj ects  engineering train  working plat-form  rise and fall  fold