摘    要:预制浮置板采用“工厂化预制、现场机械化装配”的施工工艺,测量系统是保证预制板安装精度的关键所在.采用传统基标测量系统对精调预制板已经不满足城铁浮置板地段轨道高平顺性、道床振性的要求.引入高铁CPIII控制测量技术,建立轨道精确测量控制网,可使精度和工效都大为提高.研究结果表明:其精度可以从±3 mm提高到±2 mm,工效从18 m/ (天·作业面)提高到50 m/(天·作业面).

关 键 词:预制浮置板    道床机械化装配    精度    测量控制网
收稿时间:2019-11-12

Comparative Study on Fine Adjustment Surveying Technology for Urban Rail Prefabricated Floating Slab
Authors:WANG Huiqian
Institution:WANG Huiqian (Xinyun Project Co. , Ltd. of China Railway First Group, Xianyang 712000, Shanxi, China)
Abstract:Prefabricated floating slab is prefabricated by industrialized production and assembled mechanically on site,and the surveying system is the key point to ensure the installation accuracy of the slab.The traditional benchmark surveying system against fine adjustment of prefabricated slab can not meet the requirements of high track regularity and track bed vibration in the floating slab section of urban rail.Hence high-speed railway CPⅢ control and surveying technology was introduced to establish an accurate surveying control network for rail,which increased the accuracy and work efficiency greatly.The study result shows that the accuracy increases from ± 3 mm to ± 2 mm,and the work efficiency from 18 m per day per work surface to 50 m per day per work surface.
Keywords:prefabricated floating slab  mechanical assembly of track bed  accuracy  surveying control network