分段开通城市轨道工程的系统调试
引用本文:张溢斌,吴江娇.分段开通城市轨道工程的系统调试[J].铁道通信信号,2012,48(10):40-42.
作者姓名:张溢斌  吴江娇
作者单位:北京交大微联科技有限公司,北京,100195
摘    要:轨道交通已经成为解决大城市交通问题的重要途径,各大城市也在快速进行轨道交通建设。为了使一条新线尽快投入运营,经常采用分期分段建设、开通的方案,这种建设模式给信号系统的调试带来了很大难度。在北京地铁15号线实际调试过程中发现,采用分段独立组织调试,再进行两段贯通调试的方案,可有效地保证整个项目实施的安全和进度。

关 键 词:分段开通  城市轨道工程  信号系统  调试

System Testing and Commissioning of Section Service in Urban Rail Transit Project
Zhang Yibin, Wu Jiangjiao.System Testing and Commissioning of Section Service in Urban Rail Transit Project[J].Railway Signalling & Communication,2012,48(10):40-42.
Authors:Zhang Yibin  Wu Jiangjiao
Institution:Zhang Yibin, Wu Jiangjiao
Abstract:Urban rail transit has become a most important way to solve traffic issues in big cities. Most of the big cities are constructing subway lines rapidly. In order to make a new line be put into operation as soon as possible, the government usually uses stages or sectional construction and operation scheme, which brings great difficulties to the commissioning of signaling system. We discovered that the commissioning scheme of each section was adopt independently firstly and then tested the through the commissioning of both sections in Beijing No. 15th Line, which can ensure the safety and smooth progress of the whole project effectively.
Keywords:Open and commissioning section by section  Urban rail transit project  Signaling system  Testing and commissioning