Risk Assessment of Tram Operation Based on the Fuzzy Comprehensive Evaluation Method
SHI Lijuan,ZHANG Qirui,JIN Jianfei,SUN Huize.Risk Assessment of Tram Operation Based on the Fuzzy Comprehensive Evaluation Method[J].Urban Rapid Rail Transit,2023,36(2):162-166.
Authors:SHI Lijuan  ZHANG Qirui  JIN Jianfei  SUN Huize
Institution:College of Transportation Engineering, Shanghai Tram Engineering Technology Research Center, Tongji University, Shanghai Key Laboratory of Structural Durability and System Safety of Rail Transit, Tongji University;Shanghai Urban Construction Design & Research Institute
Abstract:In this study, an operation risk assessment method combining risk event history data and expert experience was proposed to comprehensively identify and assess tram operation risks based on incomplete risk event data. By analyzing the risk event information of tram operations in northern cities in China, a hierarchical analysis method was used to identify and establish an evaluation system for key risk factors in tram operations. Subsequently, a fuzzy comprehensive evaluation method based on the risk matrix and expert evaluation methods was used to comprehensively evaluate tram operation risks. The case study of the Changchun tram operation showed that the overall risk of tram operation was acceptable, among which the risks of collision with vehicles, intrusion of foreign objects, bad weather, turnouts, and signal equipment were high. It is suggested that the relevant departments should strengthen the deployment of safety isolation facilities, supervision of personnel travel behavior, advance warnings and measures for bad weather, and intelligent maintenance and health management of key equipment in daily operations.
Keywords:tram  risk identification  risk assessment  analytic hierarchy process  export scoring method  fuzzy comprehensive evaluation method