首页 | 本学科首页   官方微博 | 高级检索  
     检索      

多跨连续箱梁悬臂施工监控技术
引用本文:杜伟.多跨连续箱梁悬臂施工监控技术[J].铁道建筑技术,2014(11):19-21.
作者姓名:杜伟
作者单位:中铁二十四局集团有限公司 上海 200071
摘    要:通过金温扩能改造工程一联多跨连续梁悬臂施工的实践,阐述各阶段施工工况,采用Midas/Civil软件建立有限元模型,检算主梁内力和挠度,计算箱梁预拱度,确定立模标高,并提出支座预偏量设置及临时固结方法。总结的监控方法可保证连续梁悬臂施工安全,成桥线形能满足设计及验标要求。

关 键 词:多跨连续梁  悬臂  线形监控

Monitoring Technology of Multi-span Continuous Box Girder Cantilever Construction
Du Wei.Monitoring Technology of Multi-span Continuous Box Girder Cantilever Construction[J].Railway Construction Technology,2014(11):19-21.
Authors:Du Wei
Institution:Du Wei ( China Railway 24^th Bureau Group Co. Ltd. , Shanghai 200071, China)
Abstract:Through the practice of a multi span continuous beam cantilever construction at the expansion project of Jinhua-Wenzhou,the paper expounds the construction condition of various stages.The finite element model is established with Mi-das/Civil software to check and calculate the internal force and deflection of main beam,calculate the pre-camber of box girder,determine the formwork elevation,and put forward the bearing pre-offset setting and temporary consolidation meth-od.The monitoring methods got through the study can ensure the safety of continuous beam cantilever construction,and the linetype of bridge can satisfy the design and standard requirements.
Keywords:multi-span continuous beam  cantilever  line shape monitoring
本文献已被 CNKI 维普 万方数据 等数据库收录!