复杂地质条件下机械化顶管施土困难对策
引用本文:樊世群.复杂地质条件下机械化顶管施土困难对策[J].筑路机械与施工机械化,2009,26(1):65-66.
作者姓名:樊世群
作者单位:西安建筑科技大学,土木工程学院,陕西,西安,710055
摘    要:结合西安一处实际工程,介绍了机械化顶管施工的施工工艺和注意事项,对机械化项管施工方法在砂土层、黏土层不同的施工情况进行了分析和总结。对今后同类型施工具有参考作用。

关 键 词:机械化顶管施工  复杂地质条件  砂土层  黏土层

Solution to Difficulty in Mechanized Construction of Pipe Jacking Under Complex Geological Condition
FAN Shi-qun.Solution to Difficulty in Mechanized Construction of Pipe Jacking Under Complex Geological Condition[J].Road Machinery & Construction Mechanization,2009,26(1):65-66.
Authors:FAN Shi-qun
Institution:FAN Shi-qun(School of Civil Engineering, Xi'an University of Architechture and Technology, Xi'an 710055, Shaanxi, China)
Abstract:The construction technology and attentions for mechanized construction of pipe jacking are introduced in combination of an actual project in Xi' an. The construction on different layers, such as sand layer and clay layer is analyzed and summarized, which provides reference for similar construction later on.
Keywords:mechanized construction of pipe jacking  complex geological condition  sand layer  clay layer