高速铁路路基接触网支柱基础施工关键技术
引用本文:苏庆国. 高速铁路路基接触网支柱基础施工关键技术[J]. 铁道建筑技术, 2014, 0(4): 96-98
作者姓名:苏庆国
作者单位:中铁十六局集团有限公司,北京100018
摘    要:随着我国铁路的迅速发展,尤其是高速铁路的发展,对铁路接触网的要求越来越高,作为接触网基础的施工也越来越受到高度重视,而接触网支柱预埋螺栓的固定尤为重要,直接关系到接触网支柱能否准确就位、受力是否合理。结合贵广铁路接触网支柱基础施工,重点介绍了接触网支柱基础预埋螺栓采用双层模具固定法施工控制关键技术,采用该施工技术,满足了设计和验标的要求。

关 键 词:高速铁路  接触网基础  施工控制

Key Technique of Catenary Mast in Foundation Construction of High-speed Railway Subgrade
Su Qingguo. Key Technique of Catenary Mast in Foundation Construction of High-speed Railway Subgrade[J]. Railway Construction Technology, 2014, 0(4): 96-98
Authors:Su Qingguo
Affiliation:Su Qingguo ( China Railway 16th Bureau Group Co. Ltd. , Beijing 100018, Chlna)
Abstract:With the rapid development of China's railway, especially the development of high-speed railway, the railway overhead catenary system has the increasingly high demand, the foundation construction is also more and more high importance, and pre-buried bolt fixed of catenary mast is particularly important, which is directly related to the catenary mast's accuracy and its stress reasonable. Combined with the construction of Guiyang-Guangzhou Railway catenary mast foundation, the paper introduces the key control construction technology of pre-buried bolt using the double mould fixing method , which satisfies the design and standard requirements.
Keywords:high-speed railway  overhead catenary system foundation  construction control