阜朝高速公路大窑沟一号隧道右线进口端冒顶处理方案 |
| |
引用本文: | 杨劲夫.阜朝高速公路大窑沟一号隧道右线进口端冒顶处理方案[J].北方交通,2007(5):162-164. |
| |
作者姓名: | 杨劲夫 |
| |
作者单位: | 辽宁省交通科学研究院,沈阳,110015 |
| |
摘 要: | 结合阜朝高速公路工程实际,分析阜朝高速公路大窑沟一号隧道右线进口端冒顶的原因,并阐述了塌方处理的方案。
|
关 键 词: | 隧道 塌方 塌方处理 施工 |
Treatments for Landslide of Entrance End of Right Curved Line of Dayaogu Tunel No. 1 on Fu - Chao Freeway |
| |
Authors: | Yang jinfu |
| |
Abstract: | In the light of reality of Fu - Chao Freeway, the paper analyzes causes for landslide of entrance end of right curved line to dayaogu tunnel No. 1 on Fu - Chao Freeway, and expounds treatments for landslide. |
| |
Keywords: | Tunnel Landslide Treatments for landslide Construction |