上中隔壁下双侧壁预锚锭工法在清华园隧道上穿地铁15号线中的应用
引用本文:凌云鹏,刘方,吕刚,王文谦,张宇宁.上中隔壁下双侧壁预锚锭工法在清华园隧道上穿地铁15号线中的应用[J].铁道勘察,2020(1):54-59.
作者姓名:凌云鹏  刘方  吕刚  王文谦  张宇宁
作者单位:中铁工程设计咨询集团有限公司
基金项目:中国铁路总公司科技研究开发计划重大课题(2017G007-B)
摘    要:为研究新建隧道近距离上穿对既有地铁隧道的变形影响,以京张高铁清华园隧道上穿北京地铁15号线区间隧道为工程背景,提出一种新的施工方法:上中隔壁下双侧壁预锚锭工法,并采用数值模拟和现场实测进行验证,分析隧道施工过程中既有地铁隧道的变形规律。研究结果表明:(1)在侧导洞扩大基础内增加预应力锚索可以有效控制15号线的上浮;(2)上中隔壁下双侧壁预锚锭工法能够保证地铁15号线的安全运营。

关 键 词:铁路隧道  数值模拟  预应力锚索  上中隔壁  下双侧壁  预锚锭工法  京张高铁

Application of Center Diaphragm in Upper Part + Double Side Heading in Lower Part + Prestressed Anchor Cable Construction Method in Qinghuayuan Tunnel Crossing over Metro Line No. 15
Ling Yunpeng,Liu Fang,Lv Gang,Wang Wenqian,Zhang Yuning.Application of Center Diaphragm in Upper Part + Double Side Heading in Lower Part + Prestressed Anchor Cable Construction Method in Qinghuayuan Tunnel Crossing over Metro Line No. 15[J].Railway Investigation and Surveying,2020(1):54-59.
Authors:Ling Yunpeng  Liu Fang  Lv Gang  Wang Wenqian  Zhang Yuning
Institution:(China Railway Engineering Design and Consulting Group Co.,Ltd.,Beijing 100055,China)
Abstract:In order to study the effect of new tunnel crossing over the existing subway tunnel on the deformation of the latter tunnel,based on the Tsinghuayuan Tunnel of Beijing-Zhangjiakou High-speed Railway crossing over Beijing Metro Line No.15,a new construction method which is named the center diaphragm in upper part+double side heading in lower part+prestressed anchor cable construction method is proposed.Numerical simulation and field measurement are used for verification,and the deformation law of existing subway tunnels during newly-built tunnel construction is obtained.The results show that:(1)adding pre-stressed anchor cable on the basis of enlarging side heading can effectively control the floatation of Line No.15;(2)the center diaphragm in upper part+double side heading in lower part+prestressed anchor cable construction method can ensure the safe operation of Metro Line No.15 in the construction process,and it has been successfully applied in Tsinghuayuan Tunnel crossing over Line No.15 at a short distance.
Keywords:Railway tunnel  Numerical simulation  Prestressed anchor cable  Center diaphragm method in upper part  Double side heading method in lower part  Prestressed anchor cable construction method  Beijing-Zhangjiakou High-speed Railway