首页 | 本学科首页   官方微博 | 高级检索  
     检索      

强富水厚层砂卵石深基坑突水三道防线技术研究
引用本文:樊玲,陈俊,尹小波,马立忠,彭述权,杜金龙.强富水厚层砂卵石深基坑突水三道防线技术研究[J].长沙交通学院学报,2012,28(2):1-7.
作者姓名:樊玲  陈俊  尹小波  马立忠  彭述权  杜金龙
作者单位:1. 中南大学资源与安全工程学院,湖南长沙410083;中南大学土木工程学院,湖南长沙410012
2. 中铁十二局集团第二工程有限公司,山西太原 030032;中南大学地球科学与信息物理学院,湖南长沙410083
3. 中南大学地球科学与信息物理学院,湖南长沙,410083
4. 中南大学资源与安全工程学院,湖南长沙,410083
5. 中南大学土木工程学院,湖南长沙,410012
基金项目:中南大学自由探索计划项目,科技支疆计划
摘    要:长沙地铁1号线省政府车站基坑长464.6m,深20m,宽20.7m.坑址范围分布超过40m深厚层砂卵石,富水性强,基坑内、外水头大,渗透系数大,地下连续墙难以穿越该地层,开挖过程中突水风险高,极易基坑底突涌.提出了多道防线预防基坑突水理念,采用三道防线综合技术(即合理增加地下连续墙深度、袖阀管法加固基坑地层和疏降水技术),预防基坑突水,加强施工监测.监测结果和工程实践表明:综合方法防基坑突水是有效的,该工程基坑突水综合预防方法对类似工程具有重要参考价值.

关 键 词:强富水  厚层砂卵石  深基坑  突水  三道防线

Study on three passes preventing water inrush for strong rich water and thick sandy pebble deep foundation pit
FAN Ling , CHEN Jun , YIN Xiao-bo , MA Li-zhong , PENG Shu-quan , DU Jin-long.Study on three passes preventing water inrush for strong rich water and thick sandy pebble deep foundation pit[J].Journal of Changsha Communications University,2012,28(2):1-7.
Authors:FAN Ling  CHEN Jun  YIN Xiao-bo  MA Li-zhong  PENG Shu-quan  DU Jin-long
Institution:1. School of Resources Safety Engineering,Central South University,Changsha 410083 ,China; 2. The 2"d Engineering CO. ,Ltd. of the lZ'h Bureau Group of China Railway,Taiyuan 030032,China; 3. School of Geoscience and Info-Physics, Central South University,Changsha 410083, China; 4. Shool of Civil Engineering ,Central South University ,Changsha 410012 ,China)
Abstract:The foundation pit of provincial government station,Changsha metro Line 1 is 464.6 m long,20 m deep and 20.7 m wide. There is strong rich water more than 40 m deep sand pebble which is big permeability coefficient and high water head between side and outside of foundation pits and is hardly penetrated by the underground continuous wall. So the water inrush risk is extremely high, and the pit bottom water inrush possi- bly happens during the foundation pit excavation. The multi-channel lines idea of pre- venting foundation pit water inrush is suggested. And specifically, the comprehensive three channel lines prevention method of the foundation pit water inrush is finished. This method includes the rational increase of underground continuous wall, sleeve valve barrel grouting method for reinforcing the foundation pit strata, drainage and dewatering tech- nology and strengthening foundation pit monitoring. The monitoring results and engi- neering practice show that the comprehensive water inrush prevention method is effec- tive. And this method can be as an important reference for similar construction.
Keywords:strong rich water  thick sandy pebble  deep foundation pit  water inrush  three passes
本文献已被 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏