DK163滑坡治理方案的回顾与反思 |
| |
引用本文: | 贺德全 张照财. DK163滑坡治理方案的回顾与反思[J]. 铁道工程学报, 1999, 0(2): 73-76 |
| |
作者姓名: | 贺德全 张照财 |
| |
作者单位: | :铁道部第一勘测设计院 岩土工程公司,兰州730000 |
| |
摘 要: | 神朔铁路DK163+750,在黄土阶坡上填筑的双线路基,沿线路长75m的路提产生了推动式工程滑坡变形,设计了抗滑挡工程。由于场地狭窄,通讯、电力线路拆迁协调困难,最终采取了清方设旱桥通过滑坡中后部的方案。大桥通车后,右侧刷方坡脚又产生了牵引式工程坡变形,增设了抗滑桩工程。本文介绍了该滑坡的发生及治理全过程。
|
关 键 词: | 工程滑波 治理 铁路路基 |
SELECTION OF TYPES AND METHODS FORTHE RESTRAINT WORKS OF LANDSLIDE AT DK163 |
| |
Abstract: | The DK163landslide located at the front flange of loess terrace in the Shenmu-Shuozhou Railway.Itoccured in double track embankment with an overall length more than 75 metres.Theanti-sliding retaining wall works were designed.Due to narrow of the site of constructionand difficulty of coordination for removal of the communication lines and the powertransmission line,finally,we take on removal landslide soil and builting viaductmeasure.After the viaduct of railway was open to traffic,the towed engineering landsildeoccured at the hillside of the soil removal works,and we take on restraint measure oflarge diameter cast-in-pile works.The paper presents mainly the geological condition,slidemechanism and restraint works. |
| |
Keywords: | |
本文献已被 维普 等数据库收录! |
|