长大斜井快速施工技术与施工管理
引用本文:高存成. 长大斜井快速施工技术与施工管理[J]. 隧道建设, 2006, 26(2): 38-40,44
作者姓名:高存成
作者单位:中铁隧道集团有限公司
摘    要:根据乌鞘岭隧道9号长大斜井的实际情况,简要介绍辅助坑道在Ⅴ、Ⅵ级围岩地质条件下实现快速施工的技术要点、机械设备配置及施工组织技术措施,初步摸索出了一整套适于软弱地质条件下长大斜井施工的施工工艺,可为类似工程提供可靠的依据和技术资料。

关 键 词:长大斜井 快速施工 技术
收稿时间:2005-09-26
修稿时间:2005-09-262006-01-10

Construction Technology and Construction Management of Long Inclined Shaft
GAO Cun-cheng. Construction Technology and Construction Management of Long Inclined Shaft[J]. Tunnel Construction, 2006, 26(2): 38-40,44
Authors:GAO Cun-cheng
Affiliation:China Railway Tunnel Group Co., Ltd
Abstract:On basis of the construction of No. 9 long inclined shaft of Wushaoling tunnel, the article briefly introduces the technical points, matching of machinery and equipment and technical measures of construction organization adopted in the construction of the inclined shaft in Grade Ⅴ and Grade Ⅵ surrounding rock mass so as to achieve high progress rate. Furthermore, the article summarizes a set of construction techniques suitable to the construction of long inclined shaft in soft ground, which can provide reliable reference and valuable technical documents for similar projects.
Keywords:long inclined shaft   rapid construction   technology