苏通大桥主跨钢箱梁水上吊装工艺及通航管理
引用本文:阚有俊.苏通大桥主跨钢箱梁水上吊装工艺及通航管理[J].船海工程,2007,36(6):74-77.
作者姓名:阚有俊
作者单位:江苏省苏通大桥建设指挥部,江苏,南通,226010
摘    要:介绍苏通大桥主跨钢箱梁吊装与通航安全管理的基本方法,通过精确计算每块箱梁吊装时所占水域情况,来评价施工对通航的影响,在此基础上,采取有针对性的通航安全管制措施,实现大桥建设与船舶通航同步进行,将施工对通航的影响降到最低限度。

关 键 词:苏通大桥  钢箱梁吊装  通航安全
文章编号:1671-7953(2007)06-0074-04
收稿时间:2007-10-06
修稿时间:2007-11-25

Analysis on Sutong Bridge main span steel box girder lifting and navigation safety management
Authors:KAN Youjun
Abstract:This article introduces basic methods to ensure navigation safety,while the main span segments were lifted,i.e.based on accurate calculation of occupied navigation area by each piece of segment lifting,assessment about influence on navigation could be attained.Navigation safety countermeasures were taken according to this,in order to realize a win-win strategy:bridge construction and available ship navigation;Finally the influence on navigation by construction was minimized.
Keywords:Sutong Bridge  steel box girder lifting  navigation safety