圆梁山隧道2#溶洞段施工技术
引用本文:陈建.圆梁山隧道2#溶洞段施工技术[J].隧道建设,2005,25(6):47-50.
作者姓名:陈建
作者单位:中铁隧道集团渝怀指挥部酉阳409800
摘    要:渝怀铁路23标段圆梁山隧道2#溶洞位于毛坝向斜的高压富水段,水平剖面纵向宽度50m,在部分泄水的条件下测试水压为3.013MPa,且溶洞内富含粉细砂。本文主要介绍2#溶洞段顺利地实现全断面贯通的开挖施工技术。

关 键 词:高水位  富水段  溶洞  隧道  开挖技术
收稿时间:2004-09-06
修稿时间:2004年9月6日

Construction Technology of No.2 Karst Cave Section of Yuanliangshan Tunnel
CHEN Jian.Construction Technology of No.2 Karst Cave Section of Yuanliangshan Tunnel[J].Tunnel Construction,2005,25(6):47-50.
Authors:CHEN Jian
Institution:Yu Huai Railway Construction Headquarters of China Railway Tunnel Group Co., Ltd.,
Youyang 409800, Chongqing|China
Abstract:No.2 karst cave of Yuanliangshan Tunnel on Yu Huai railway is located in the Maoba syncline section where there exists rich high pressured water. The longitudinal width of the level profile of No. 2 karst cave is 50m. The water pressure measured under the condition of partial water discharge is 3.013 MPa. Furthermore, the karst cave contains a large amount of fine silt sand. The emphasis of the article is placed on the introduction of the excavation technology adopted in the full face breakthrough of No.2 karst cave section of the tunnel.
Keywords:high water level  waterrich section karst cave  tunnel  excavation technology