造船分段无余量合拢挂装工艺初探
引用本文:牟永生.造船分段无余量合拢挂装工艺初探[J].造船技术,2012(3):35-36,51.
作者姓名:牟永生
作者单位:青岛北海船舶重工有限责任公司,山东青岛,266520
摘    要:造船分段无余量合拢挂装工艺,把待合拢分段挂装在已经完成的分段上,使挂件、支撑件承载60%至70%待合拢分段的重量,消除了90%以上因吊装产生的弹性变形,实现了造船分段无余量合拢.该工艺比传统工艺提高工效1倍以上,使造船在坞合拢时间缩短53天,使年出船艘数增加30%,并较大的降低了生产成本.

关 键 词:分段  无余量合拢  挂装工艺

Research of the Optimally Sized Block Assembly and Hanging Erection Process in Shipbuilding
MU Yong-sheng.Research of the Optimally Sized Block Assembly and Hanging Erection Process in Shipbuilding[J].Journal of Marine Technology,2012(3):35-36,51.
Authors:MU Yong-sheng
Institution:MU Yong-sheng (Qingdao Beihai Shipbuilding Heavy Industry Co.LTD,Qjngdao Shandong 266520,China)
Abstract:The optimally sized block assembly and hanging erection process,is to erect the structure of the block to the finished blocks with hanging equipments.This process eliminated over 90%of the elasticity change of shapes due to crane enabled welding by diversifying 60%to 70%of the assembly blocks’ weight to the hanging and supporting parts.This process increases the shipbuilding efficiency by 100%,shortens the time in building dock by 53 days, increases the number of ships finished by 30%annually,and lowers the production cost significantly.
Keywords:Block  Optimally sized block assembly  Hanging erection process