针梁式全圆模板台车在海底引水隧洞工程衬砌施工中的创新应用
引用本文:陈启伟,王亚利,张建.针梁式全圆模板台车在海底引水隧洞工程衬砌施工中的创新应用[J].隧道建设,2013,33(8):690-695.
作者姓名:陈启伟  王亚利  张建
作者单位:(1.盾构及掘进技术国家重点实验室, 河南 郑州 450001; 2.中铁隧道集团有限公司, 河南 洛阳 471009; 3.济源市华泰测绘有限公司, 河南 济源 459000; 4.中铁隧道股份有限公司台山核电站取水隧洞项目部, 广东 台山 529200)
基金项目:国家国际科技合作专项资助,洛阳市应用技术研究与开发资金项目,中铁隧道集团科技创新计划项目,中国中铁股份有限公司科技开发计划项目
摘    要:为了解决海底引水隧洞衬砌混凝土施工全圆一次成型和长距离隧洞衬砌施工短工期内快速完成等诸多问题,选用针梁式全圆模板台车对台山核电站取水隧洞工程进行二次衬砌施工。分析长大隧洞二次衬砌总体施工方法及流程,详细介绍模板台车的构造及主要技术参数,阐述模板台车关键施工工艺和技术。结合工程概况和工期要求,总结了以下3个创新应用结论: 在3台模板台车连续跳板作业条件下,隧道内、外的施工布局和流程设计; 3台模板台车一次性灌注整体模板连续跳板衬砌施工的工艺和方法; 3台模板台车连续跳板流水线作业施工注意事项。

关 键 词:海底隧洞  针梁式全圆模板台车  单向同步衬砌  连续跳板
收稿时间:2013-03-29

Innovative Application of Needle-beam Full-circular Formwork Jumbos in Construction of Lining of Sub-sea Water-diversion Tunnel
CHEN Qiwei , WANG Yali , ZHANG Jian.Innovative Application of Needle-beam Full-circular Formwork Jumbos in Construction of Lining of Sub-sea Water-diversion Tunnel[J].Tunnel Construction,2013,33(8):690-695.
Authors:CHEN Qiwei  WANG Yali  ZHANG Jian
Institution:(1. State Key Laboratory of Shield Machine and Boring Technology, Zhengzhou 450001, Henan, China; 2. China Railway Tunnel Group Co., Ltd., Luoyang 471009, Henan, China;  3. Jiyuan Huatai Surveying and Mapping Co., Ltd., Jiyuan 459000, Henan, China;  4. Management Department of Intake Tunnel of Taishan Nuclear Power Station, China Railway Tunnel Stock Co., Ltd., Taishan 529200, Guangdong, China)
Abstract:Needle beam full circular formwork jumbos are used in the construction of the secondary lining of the intake tunnel of Taishan Nuclear Power Plant, so as to realize once for all and rapid construction of the full circular concrete lining of the sub sea water diversion tunnel. In this paper, the method and procedure of the construction of the secondary lining are analyzed, the main structure and technical parameters of the formwork jumbos are presented, and the key construction technologies are described. Furthermore, three innovative points of the application of the formwork jumbos, including the construction arrangement and design inside and outside of the tunnel in the case of 3 formwork jumbos, the continuous construction of the lining by means of 3 formwork jumbos and the cautions for the continuous construction of the lining by 3 formwork jumbos, are summarized.
Keywords:sub-sea tunnel  needle-beam full-circular formwork jumbo  one-way synchronized lining  continuous operation in turn