霞浦隧道穿过富水破碎F1断层的综合治理措施
引用本文:陈丽萍.霞浦隧道穿过富水破碎F1断层的综合治理措施[J].国防交通工程与技术,2009,7(2):38-41.
作者姓名:陈丽萍
作者单位:中铁十九局集团有限公司,辽宁,辽阳,111000
摘    要:霞浦隧道F1断层富水而破碎,施工中发生塌方和涌水的可能性很大。对此采用超前地质探查、超前预注浆阻水、加设大管棚、加强初期支护、加固圈3m全断面径向注浆、加强防、排水等一系列综合治理措施,成功地通过了F1断层。施工经验可供同类工程参考。

关 键 词:断层破碎带  隧道  施工  预注浆阻水  全断面径向注浆

Comprehensive Treatment Measures for the Section of the Xiapu Tunnel Through F1 Watery Broken Fault
Chen Liping.Comprehensive Treatment Measures for the Section of the Xiapu Tunnel Through F1 Watery Broken Fault[J].Traffic Engineering and Technology for National Defence,2009,7(2):38-41.
Authors:Chen Liping
Institution:19th Bureau Group of the Railway Building Corporation of China;Liaoyang 111000;China
Abstract:The F1 fault through which the Xiapu Tunnel goes is watery and broken,which is most likely to result in collapse and gush of underground water in the process of construction.With the poor geological conditions taken into account,taken are a few comprehensive treatment measures,such as the advanced geological exploration,pre-slip-casting concrete to stop water,building the large-tube shed,strengthening the initial support,full-section radial slip casting concrete onto the 3 m strengthening ring,strengthening...
Keywords:broken fault belt  tunnel  construction  pre-slip-casting concrete to stop water  full-section radial slip-casting  