简支转连续梁桥施工程序对结构内力影响分析
引用本文:高云峰,叶元芬.简支转连续梁桥施工程序对结构内力影响分析[J].重庆交通学院学报,2006,25(B06):35-37,43.
作者姓名:高云峰  叶元芬
作者单位:重庆交通大学,重庆400074
摘    要:简支转连续梁桥在施工阶段存在体系转换,不同的施工程序会对结构内力产生影响.通过5跨30m箱梁的具体工程实例,针对15种不同的施工程序进行计算分析.分析表明:先浇筑整体化层后浇筑湿接缝或整体化层与湿接缝交替浇筑对结构受力更有利;梁端湿接缝的预应力张拉顺序在施工阶段也会对结构内力产生一定的影响.

关 键 词:简支转连续  施工程序  内力分析  张拉顺序
文章编号:1001-716X(2006)S1-0035-03
收稿时间:2006-05-29
修稿时间:2006-05-29

Analysis on the influence of orders of construction on the structural internal force in continuous beam bridge erected by many of simply supported beams
GAO Yun-feng, YE Yuan-fen.Analysis on the influence of orders of construction on the structural internal force in continuous beam bridge erected by many of simply supported beams[J].Journal of Chongqing Jiaotong University,2006,25(B06):35-37,43.
Authors:GAO Yun-feng  YE Yuan-fen
Institution:Chongqing Jiaotong University, Chongqing 400074, China
Abstract:
Keywords:continuous erection by many of simply supported beams  order of construction  internal force analysis  tension sequence