桥梁支座更换设计 |
| |
引用本文: | 张大伟.桥梁支座更换设计[J].北方交通,2012(5):96-98. |
| |
作者姓名: | 张大伟 |
| |
作者单位: | 辽宁省交通规划设计院,沈阳,110166 |
| |
摘 要: | 对目前国内广泛使用的更换支座的方法进行了分析总结,在内蒙古大广高速赤峰至茅荆坝(蒙冀界)段公路工程中采用了一种安全可靠、省时省力的支座更换方法 -同步顶升系统;对该法的设计、作用原理进行了阐述,并介绍了其施工过程,为更换桥梁支座提供参考。
|
关 键 词: | 桥梁支座 同步顶升系统 整体顶升 PLC |
Replacement Design for Bridge Support |
| |
Authors: | ZHANG Da-wei |
| |
Institution: | ZHANG Da-wei |
| |
Abstract: | The widely-used methods at home for replacing support at present are analyzed and summarized.In highway project of Chifeng-Maojing Dam(boundary of Inner Mongolia and Hebei) of Daguang Expressway,a kind of safe,reliable and time-saving method for replacing support-synchronization lifting system is adopted.The design and action principle of this method is elaborated and the construction process is introduced,thus providing references for replacement of bridge support. |
| |
Keywords: | Bridge support Synchronization lifting system Integrated lifting PLC |