组合工便梁在既有线框构桥顶进施工中的应用
引用本文:张永全,夏龙.组合工便梁在既有线框构桥顶进施工中的应用[J].辽宁交通科技,2014(2):1-5.
作者姓名:张永全  夏龙
作者单位:中铁一局集团第五工程有限公司,宝鸡721006
摘    要:摘要:在铁路既有线的框构桥顶进施工中,线路加固方式受框构跨度、限界及限速等条件约束。根据1—9.Om框构桥顶进施工的实例,结合D型便梁和吊轨横抬梁的特点,设计并采用了组合工便梁法进行线路加固,由于该加固体系受约束条件少适应范围大,故对其结构组成、主要构件设计检算、施工顺序及技术要点等进行介绍,便于类似工程参考和比选。

关 键 词:铁路既有线  线路加固  线路架空  组合工便梁  框构桥  顶进

The Application of Combined I -Beam Jacking Construction on the Existing Frame Structure Bridge
Abstract:In the jacking construction of railway existing frame structure bridge, the circuit reinforcement methods are limited by conditions such as frame structure span, range limit and speed limit. According to 1 -9. Om frame structure bridge jacking construction and with the features of D - type girder and overhead horizontal beams, combined I -beam are designed and used to reinforce the circuit. Because the reinforcement system has a wide adaptive norm with few constraint conditions, its structural compositions, design and check of primary members, construction sequence and technical points are introduced in order to give a reference and comparison to relevant projects.
Keywords:Railway existing line  Circuit reinforcement  Circuit off - contact  Combined I - type beam  Frame structure bridge  Jacking
本文献已被 维普 等数据库收录!