首页 | 本学科首页   官方微博 | 高级检索  
     检索      

京九铁路电气化改造工程供置方案优化
引用本文:张立志,韩学军.京九铁路电气化改造工程供置方案优化[J].电气化铁道,2010,21(2):26-27.
作者姓名:张立志  韩学军
作者单位:中铁电气化局集团第一工程有限公司,北京,100087
摘    要:电气化铁道直供供电方式区段,以往供电线采取沿铁路独立布置的方式,本文提出了接触网支柱与供电线支柱采取交叉异侧布置的方案,以及如何避免牵引变电所、分区所的馈线与供电线出现交叉的方法。对类似电气化施工提供了新的思路和方法。

关 键 词:直供供电方式  供电线  布置  交叉异侧

Optimized Power Supply Wiring Plan for Beijing-Kowloon Railway Electrification Reconstruction Project
ZHANG Li-zhi,HAN Xue-jun.Optimized Power Supply Wiring Plan for Beijing-Kowloon Railway Electrification Reconstruction Project[J].Electric Railway,2010,21(2):26-27.
Authors:ZHANG Li-zhi  HAN Xue-jun
Abstract:Formerly the power feeder adopts the independent arrangement along the railroad in the section of electric railway direct-feeding system. The paper proposes a new scheme that the OCS mast and the power feeder mast adopt cross-different side arrangement, and proposes a method that how to avoid the cross between the feeder and the power feeder in the traction substation. It is provided new ideas and methods to the similar construction of the electric railway.
Keywords:direct-feeding system  power feeder  arrange  cross-different side  
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号