先填后挖法在隧道塌方中的应用
引用本文:赵喜科.先填后挖法在隧道塌方中的应用[J].铁道建筑技术,2014(12):33-35.
作者姓名:赵喜科
作者单位:中铁二十四局集团有限公司 上海 200071
摘    要:在隧道埋深较大位置出现大塌方,地表无法直接注浆回填和明挖时,选用具有较好流动性的轻质混凝土材料,超前灌筑满塌方顶部空腔及固结已塌方的石碴,同时设置超前大管棚贯通整个塌方体,将塌方段处理转换成隧道常规的软弱围岩暗挖施工,通过采用合理的开挖工法和安全控制措施,极大降低了塌方处理的风险。

关 键 词:先填后挖法  超前大管棚  轻质混凝土

The Application of Post-filling Excavation in Tunnel Collapse
Zhao Xike.The Application of Post-filling Excavation in Tunnel Collapse[J].Railway Construction Technology,2014(12):33-35.
Authors:Zhao Xike
Institution:Zhao Xike (China Railway 24^th Bureau Group Co. Ltd. , Shanghai 200071 , China)
Abstract:When big collapse occurs in deep buried tunnel and there is no condition for backfill grouting or cut cover tunnels,light concrete with good liquidity should be used to pre-grout the top empty cavity and consolidate the collapse slag fully; meanwhile,the advanced large pipe shed should be set through the whole collapse. In this way,the collapse construction is converted to underground excavation for regular tunnel weak surrounding rock. It can reduce the risks of collapse treatment to the utmost by reasonable excavation method and safety control measures.
Keywords:post-filling excavation method  advanced large pipe shed  light concrete