富水砂砾地层盾构液氮冻结常压开仓施工技术
引用本文:刘占英,赵书银,姜景双,吴浩,魏清波.富水砂砾地层盾构液氮冻结常压开仓施工技术[J].铁道建筑技术,2020(2):81-84,92.
作者姓名:刘占英  赵书银  姜景双  吴浩  魏清波
作者单位:呼和浩特市城市轨道交通建设管理有限责任公司;中铁十六局集团有限公司;中铁十六局集团北京轨道交通工程建设有限公司;中铁十九局集团轨道交通工程有限公司
摘    要:为了解决富水砂砾地层中盾构区间前盾范围的土体加固,使得盾构机具备常压开仓换刀的条件,考虑到液氮气化时剧烈吸热的原理,提出了采用液氮冻结技术快速冻结土体的解决思路。通过地面施工垂直钻孔,并下放液氮冻结管,液氮气化吸热,直至冻结面及周围土体,对盾构机前盾1.5 m范围的土体加固。实践证明,在富水砂砾地层中其它封水措施效果达不到安全要求的情况下,液氮快速冻结技术取得了理想效果。

关 键 词:盾构隧道  常压开仓  土体加固  液氮冻结  富水砂砾地层

Construction Technology for Shield Opening Chamber at Atmospheric Pressure in Water-rich Sand and Gravel Strata
LIU Zhanying,ZHAO Shuyin,JIANG Jingshuang,WU Hao,WEI Qingbo.Construction Technology for Shield Opening Chamber at Atmospheric Pressure in Water-rich Sand and Gravel Strata[J].Railway Construction Technology,2020(2):81-84,92.
Authors:LIU Zhanying  ZHAO Shuyin  JIANG Jingshuang  WU Hao  WEI Qingbo
Institution:(Hohhot City Rail Transit Construction Management Co.Ltd.,Hohhot Inner Mongolia 010000,China;China Railway 16th Bureau Group Co.Ltd.,Beijing 100020,China;China Railway 16th Bureau Group Beijing Metre Engineering Conseuction Co.Ltd.,Beijing 101149,China;China Railway 19th Bureau Group Metre Engineering Co.Ltd..Beijing 101300,China)
Abstract:In order to solve soil reinforcement at the front of shield in water-rich sand and gravel strata,the condition was satisfied for shield to open chamber at atmospheric pressure.Solution thought was proposed to rapidly freeze soil by liquid nitrogen freezing technology in consideration of the principle of vigorous heat absorption during liquid nitrogen gasification.The soil was reinforced at the 1.5 m ahead of shield by vertical drilling from ground surface,placing down the freezing pipe of liquid nitrogen.Liquid nitrogen was gasified to absorb heat until freezing ahead and around soil.The practice proved that ideal result was reached for liquid nitrogen to rapidly freeze,when other measures of prevention water couldn’t meet safe demand in water-rich sand and gravel strata.The research result could provide certain reference for similar complex geological conditions of shield to open chamber and change cutting tools at atmospheric pressure.
Keywords:shield tunnel  opening chamber at atmospheric pressure  soil reinforcement  freezing of liquid nitrogen  water-rich sand and gravel strata