宁芜线青弋江特大铁路桥施工技术研究
引用本文:马木欣.宁芜线青弋江特大铁路桥施工技术研究[J].交通科技,2014(2):51-53.
作者姓名:马木欣
作者单位:中铁第四勘察设计院集团有限公司, 武汉 430063
摘    要:以宁芜线青弋江大桥主桥2×88m系杆拱施工为背景,介绍了在1年工期内,靠近既有线、限净空条件下,主梁系杆拱先梁后拱、上部结构和下部结构统筹考虑的快速施工技术,不但满足了施工工期的要求,而且很好地规避了施工风险。

关 键 词:钢管拱桥  先梁后拱  快速施工技术  限净空

Research on Construction Technology of Qing YiJiang Railway Bridge in NingWu Line
Ma Muxin.Research on Construction Technology of Qing YiJiang Railway Bridge in NingWu Line[J].Transportation Science & Technology,2014(2):51-53.
Authors:Ma Muxin
Institution:Ma Muxin (China Railway Siyuan Survey and Design Group Co. ,Let. , Wuhan 430063, China)
Abstract:Qingyi River Bridge locates on NingWu Line.It is a tied-arch bridge with a span of 2×88m. It only takes a year to complete the construction,although it is close to the existing line.Under the condition of limited clearance,the method of erecting girder first and arch late is used.The construc-tion of the superstructure and substructure is coordinated and implemented by using rapid construction technologies.The way to build the bridge not only meets the requirements of the construction period, but also avoids construction risks very well.The successful completion of the bridge provides practical basis for the similar projects.
Keywords:steel pipe arch bridge  erecting girder first and arch late  rapid construction  limit clear-ance