移动模架墩旁托架荡移安装与拆除技术
引用本文:汤得志,刘福星.移动模架墩旁托架荡移安装与拆除技术[J].交通科技,2014(2):65-67.
作者姓名:汤得志  刘福星
作者单位:中交二航局第五工程分公司, 武汉 430012
摘    要:以福银高速九江长江公路大桥副孔桥连续箱梁移动模架施工为背景,介绍了移动模架墩旁托架荡移安装和拆除技术。在施工成本及安全的双控前提下,采用墩旁托架吊具进行移动模架墩旁托架安装,钢丝绳通过预留孔荡移进行墩旁托架拆除,顺利完成了墩旁托架的安拆任务。

关 键 词:墩顶吊具  荡移  预留孔

Move Support System Bracket Installation and Removal Technology That the Swing Shift Method
Tang Dezhi,Liu Fuxing.Move Support System Bracket Installation and Removal Technology That the Swing Shift Method[J].Transportation Science & Technology,2014(2):65-67.
Authors:Tang Dezhi  Liu Fuxing
Institution:(The 5th Branch Company of the Second Harbour Engineering Co. ,Ltd. ,CCCC , Wuhan 430012, China)
Abstract:Based on the project of vice-hole bridge continuous box girder using move support system construction of Jiujiang Yangtze Bridge on Fuzhou-Yinchuan expressway,this paper introduces the in-stallation and removal technology of movable formwork bracket.On the premise of construction cost and safety,the installation and removal of the pier-side supporting structures are completed success-fully by moving die carrier and swing shift of wire rope wearing into the reserved hole.
Keywords:pier top sling  swing shift  reserved hole