首页 | 本学科首页   官方微博 | 高级检索  
     检索      

寒区隧道洞口衬砌开裂和道床冰害原因分析及整治
引用本文:郑波,吴剑,陈建平.寒区隧道洞口衬砌开裂和道床冰害原因分析及整治[J].隧道建设,2017,37(7):864-871.
作者姓名:郑波  吴剑  陈建平
作者单位:(1. 中铁西南科学研究院有限公司, 四川成都 611731; 2. 中铁八局集团有限公司, 四川成都 610036)
基金项目:中国中铁股份有限公司科技开发计划项目课题(2012-重大-08; 2014-重点-26)
摘    要:为解决寒冷地区隧道内部产生的冰害问题,以东北地区某铁路隧道为例,采用综合分析的方法,对案例隧道洞口衬砌开裂、渗水以及道床冰害产生的原因进行研究,并提出相应的整治措施。研究结果表明:1)隧道洞口围岩衬砌开裂主要由围岩冻胀力引起,采用喷涂保温层+防火砂浆的保温措施以及锚杆补强和裂缝嵌补的结构措施可以有效避免衬砌的开裂;2)引起道床冰害的洞内水主要来源于洞口路堑的积雪融化水和仰拱局部渗水,采用双侧水沟布设电加热设施、洞口道床底部设置小型挡水坝并加设横向电加热设施和进口路堑位置及路堤零填段设置挡雪设施的措施可以有效解决道床冰害问题。

关 键 词:铁路隧道  冻胀力  衬砌开裂  道床冰害  保温措施  电加热设施
收稿时间:2016-11-08

Analysis of Causes of Lining Cracking and Ballast Bed Freezing at Railway Tunnel Portal in Cold Regions and Their Countermeasures
ZHENG Bo,WU Jian,CHEN Jianping.Analysis of Causes of Lining Cracking and Ballast Bed Freezing at Railway Tunnel Portal in Cold Regions and Their Countermeasures[J].Tunnel Construction,2017,37(7):864-871.
Authors:ZHENG Bo  WU Jian  CHEN Jianping
Institution:(1. China Railway Southwest Research Institute Co., Ltd., Sichuan 611731, Chengdu, China; 2. China Railway No.8 Engineering Group Co., Ltd., Sichuan 610036, Chengdu, China)
Abstract:The causes of lining cracking, water leakage and ballast bed freezing at portal section of a railway tunnel in Northeast China are analyzed by comprehensive analysis method; and then relevant countermeasures are proposed. The analytical results show that: 1) The cracking of surrounding rock lining is mainly caused by frost heave force of surrounding rock; and it can be effectively avoided by using insulation measure of spraying insulation layer + fireproof mortar and structural reinforcement measure of anchor bolt + crack filling. 2)The water caused ballast bed freezing in tunnel is mainly derived from snow on portal cutting of tunnel and the local water leakage of inverted arch; and it can be effectively avoided by setting electric heating facilities in ditches on both sides of the tunnel, setting a small dam and horizontal electric heating facilities under the bottom of ballast bed, and setting snow covered facilities on portal cutting of tunnel and zero fill section of embankment.
Keywords:railway tunnel  frost heave force  lining cracking  ballast bed freezing  insulation facility  electric heating facility
本文献已被 CNKI 等数据库收录!
点击此处可从《隧道建设》浏览原始摘要信息
点击此处可从《隧道建设》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号