连续曲线梁桥整体调坡顶升关键技术
引用本文:尹天军.连续曲线梁桥整体调坡顶升关键技术[J].城市道桥与防洪,2020(6):147-150,M0016.
作者姓名:尹天军
作者单位:1.上海先为土木工程有限公司
摘    要:以南通市长江北路西延(沿海公路-城北大道)高架桥为工程背景,对连续曲线梁桥的整体调坡顶升方案进行了系统的研究,并就连续曲线梁调坡顶升过程中,如何保持等比例顶升、保证千斤顶与上部箱梁垂直、限制千斤顶水平位移等方面提出了解决方法,相关技术方案及施工方法可为同类桥梁规划改造提供参考。

关 键 词:连续曲线梁桥  调坡顶升  等比例顶升  施工技术

Key Technology of Overall Slope Adjusting and Jacking for Continuous Curved Beam Bridge
YIN Tianjun.Key Technology of Overall Slope Adjusting and Jacking for Continuous Curved Beam Bridge[J].Urban Roads Bridges & Flood Control,2020(6):147-150,M0016.
Authors:YIN Tianjun
Abstract:Based on the engineering background of Nantong North Changjiang Road West Extension(Yanhai Highway-Chengbei Avenue)Viaduct,the overall slope adjusting and jacking scheme of continuous curved beam bridge is systematically studied.The solution is proposed how to keep the equal proportion of jacking,to guarantee the jack to be perpendicular with the upper box beam and to limit the horizontal displacement of the jack in the process of slope adjusting and jacking of continuous curved beam.The relative technical scheme and the construction method can be referred for the planning and reconstruction of the similar bridges.
Keywords:continuous curved beam bridge  slope adjusting and jacking  equal proportion of jacking  construction technology