PC系杆拱桥施工阶段稳定性及临时横撑影响分析
引用本文:郑晓燕,周跃,瞿芹,吴文清.PC系杆拱桥施工阶段稳定性及临时横撑影响分析[J].桥梁建设,2012,42(1):67-71.
作者姓名:郑晓燕  周跃  瞿芹  吴文清
作者单位:1. 南京林业大学土木工程学院,江苏南京,210037
2. 东南大学交通学院,江苏南京,210096
摘    要:为有效指导PC系杆拱桥的施工,对该类桥梁施工阶段的稳定性及临时横撑对结构稳定性的影响进行研究.以江苏省新建省道336公路桥为背景,采用MIDAS Civil建立桥梁空间有限元模型,对3个施工控制阶段结构的稳定性及临时横撑设置与否、设置位置及形式对暂态拱稳定性的影响进行分析.分析结果表明:该桥施工阶段具有较好的稳定安全系数;施工阶段的吊杆张拉对全桥的稳定性有负影响;对称设置临时横撑时,同类型横撑设置在1/4跨径处效果最为明显;在相同位置设置X形临时横撑对结构稳定性贡献最大;横撑的间距和形式选择还需综合考虑桥梁美学、经济性及施工方便.

关 键 词:系杆拱桥  临时横撑  稳定性  施工阶段  有限元法

Analysis of Stability and Influences of Temporary Cross Bracings of PC Tied Arch Bridge at Construction Stages
ZHENG Xiao-yan , ZHOU Yue , QU Qin , WU Wen-qing.Analysis of Stability and Influences of Temporary Cross Bracings of PC Tied Arch Bridge at Construction Stages[J].Bridge Construction,2012,42(1):67-71.
Authors:ZHENG Xiao-yan  ZHOU Yue  QU Qin  WU Wen-qing
Institution:1.College of Civil Engineering,Nanjing Forestry University,Nanjing 210037,China; 2.School of Transportation,Southeast University,Nanjing 210096,China)
Abstract:To provide effective guidance for the construction of prestressed concrete(PC) tied arch bridge,the stability of the bridge of the same type and the influences of temporary cross bracings on the stability at construction stages were studied.The Highway Bridge 336 on the Provincial Route,Jiangsu was cited as an example,the MIDAS Civil was used to create the spatial finite element model for the bridge,the stability and influences of setting or not setting the temporary cross bracings,positions and types of the bracings at three construction stages on the stability of the arch in temporary status were analyzed.The results of the analysis show that the bridge at the construction stages has good stability safety coefficients.At the construction stages,the tensioning of hangers has negative influence on the stability of the whole bridge.When the temporary cross bracings are symmetrically set,the effect of the bracings of the same type set at 1/4 span is most obvious and the contribution of the X-shape temporary bracings set at the same positions to the stability is the greatest.However,for selection of the spacing distance and types of the bracings,the factors of the aesthetics,economy and construction convenience of the bridge should be comprehensively considered.
Keywords:tied arch bridge  temporary cross bracing  stability  construction stage  finite element method