桩锚加固边坡的作用机理和稳定性分析研究
引用本文:方理刚,孙正兵,王强.桩锚加固边坡的作用机理和稳定性分析研究[J].中南公路工程,2007,32(4):152-155,166.
作者姓名:方理刚  孙正兵  王强
作者单位:中南大学土木建筑学院 湖南长沙410075(方理刚,孙正兵),中铁大桥勘测设计研究院 湖北武汉436400(王强)
摘    要:由某高速公路现场钻孔资料和地质调查分析得知,路基开挖后该边坡处于临滑状态。应用极限平衡原理,通过反演分析,求得滑动面的粘聚力c和内摩擦角φ。由锚索提供的水平抗力对自由段求极值确定锚索最优安装角。运用有限元法对纯桩和桩锚复合加固方案进行对比,计算出边坡上部经加固后向下传递的荷载。结果表明,桩锚方案加固效果显著。边坡锚索的预应力损失监测分析表明,锚索在锁定后470 d内的预应力损失为7.8%~12.9%,满足工程安全要求。工后2 a的运营阶段边坡处于稳定状态。

关 键 词:预应力锚索抗滑桩  滑坡处理  锚索监测  有限元评价  稳定性
文章编号:1002-1205(2007)04-0152-04
收稿时间:2006-10-25
修稿时间:2006-10-25

The analysis of mechanism and stability of slope reinforced with the pre-forced cable and anti-slipping Pile
FANG Ligang, SUN Zhengbing, WANG Qiang.The analysis of mechanism and stability of slope reinforced with the pre-forced cable and anti-slipping Pile[J].Central South Highway Engineering,2007,32(4):152-155,166.
Authors:FANG Ligang  SUN Zhengbing  WANG Qiang
Institution:1. School of Civil Engineering and Architecrure, Central South University, Changsha, Hunan 410075, China; 2. China Zhongtie Major Bridge Reconnaissance and Design Institute, Wuhan, Hubei 436400, China
Abstract:As is known from the monitoring in-situ and geology, on an expressway the newly-cut slope is in the limit equilibrium status. According to limit equilibrium principle of slope, a back analysis has been made to get the cohesive factor c and internal friction angle tp of pre-existing potential instable discontinuities. And the fixing angle of cable is determined by the extremum of the aclinic anti-slipping force to free section. The FEM is adopted to compare the scheme of anti-slipping pile with the pre-forced cable and anti-slipping pile, and calculate the load transfered from the above reinforced slope. The result indicates that the reinforcing effect is distinct in the scheme of pre-forced cable and anti-slipping pile. Moreover,by monitoring and analyzing the loss of pre-force in the cables we find the range of it is 7.8% - 12.9% in 470 days after itg been fixed,which meets the demand of project safety. In the following 2 years in function, the slope can maintain stability .
Keywords:Anti-slipping pile with Pre-forced cable  Slope treatment  Monitoring of cable  Evaluation with FEM  Stability
本文献已被 CNKI 维普 等数据库收录!