预偏补偿悬臂端位移在钢桁架拱桥跨中无应力合拢施工中的应用
引用本文:孙玉祥,汪存书,蔡新民.预偏补偿悬臂端位移在钢桁架拱桥跨中无应力合拢施工中的应用[J].水运工程,2010(1).
作者姓名:孙玉祥  汪存书  蔡新民
作者单位:中交第二航务工程局有限公司第二工程有限公司,重庆,400042
摘    要:重庆朝天门长江大桥是目前世界上最大跨度的拱桥,设计无应力跨径为190 m+552 m+190 m,从边支点向跨中悬臂安装.采取预偏施工技术,调整边、中支点高差及位移,补偿合拢口高差及位移,成功实现桁拱跨中无应力合拢,可供类似工程施工参考.

关 键 词:钢桁架拱桥  预偏补偿法  无应力合拢

Application of pre-deviation compensation for cantilever end displacement in non-stress closure construction at mid-span steel truss arch bridge
SUN Yu-xiang,WANG Cun-shu,CAI Xin-min.Application of pre-deviation compensation for cantilever end displacement in non-stress closure construction at mid-span steel truss arch bridge[J].Port & Waterway Engineering,2010(1).
Authors:SUN Yu-xiang  WANG Cun-shu  CAI Xin-min
Institution:SUN Yu-xiang,WANG Cun-shu,CAI Xin-min(China Communications 2nd Harbor Bureau 2nd Engineering Co.,Ltd,Chongqing 400042,China)
Abstract:Chongqing Chaotianmen Yangtze River Bridge is the largest arch bridge in span currently in the world with a design non-stress span of 190 m+552 m+190 m,installed from side bearing point to mid-span cantilever.This paper uses pre-deviation construction technique to successfully achieve non-stress closure at the mid-span by adjusting the elevation difference and displacement between side and middle bearing points to compensate the elevation difference and displacement at the closure opening,serving as a refer...
Keywords:steel truss arch bridge  pre-deviation compensation method  non-stress closure  