首页 | 本学科首页   官方微博 | 高级检索  
     检索      

无掩护海域复杂地质条件下的灌注桩施工
引用本文:冯建国,汪洪祥,姜宁林.无掩护海域复杂地质条件下的灌注桩施工[J].水运工程,2019(5):184-188.
作者姓名:冯建国  汪洪祥  姜宁林
作者单位:中交第二航务工程勘察设计院有限公司,湖北 武汉 430060,中国港湾工程有限责任公司,北京 100027,中交第二航务工程勘察设计院有限公司,湖北 武汉 430060
摘    要:桩基础的施工是高桩墩台结构施工的关键,尤其是在无掩护海域、无覆盖层复杂地质条件下的灌注桩施工,影响因素多、技术难度高。结合巴基斯坦某电厂码头引桥灌注桩施工的实际情况,从施工条件、关键施工工艺等环节展开分析。结果表明:针对无覆盖层地质下的钻孔灌注桩施工,钢护筒施工建议采用打钻结合、复打二次跟进的施工工艺;为保证桩基垂直度,施工中需针对具体桩基情况设计相应的打桩导向架;水下钻孔灌注施工过程中如遇异常问题,应立即暂停施工,提出针对性的解决方案后方可继续施工。

关 键 词:无掩护海域  复杂地质  灌注桩  钢护筒  钻孔  施工技术

Construction of bored pile under complicated geological conditions in unshielded sea area
FENG Jian-guo,WANG Hong-xiang and JIANG Ning-lin.Construction of bored pile under complicated geological conditions in unshielded sea area[J].Port & Waterway Engineering,2019(5):184-188.
Authors:FENG Jian-guo  WANG Hong-xiang and JIANG Ning-lin
Institution:CCCC Second Harbor Consultants Co.,Ltd.,Wuhan 430060,China,China Harbor Engineering Co.,Ltd.,Beijing 100027,China and CCCC Second Harbor Consultants Co.,Ltd.,Wuhan 430060,China
Abstract:The construction of pile foundation is the key to the construction of high pile supported dolphin structure,especially the construction of bored pile under complicated geological conditions in unshielded sea area due to many influencing factors and high technical difficulty.Based on the actual construction situation of bored pile for wharf approach bridge of a power plant in Pakistan,the construction conditions and key construction techniques are analyzed.The analysis results show that:for bored pile construction without overburden geology,steel casing construction is suggested to adopt the construction technology of combination of drilling and re-drilling;in order to ensure the perpendicularity of pile foundation,the corresponding piling guide frame should be designed according to the specific pile foundation conditions;in the process of underwater bored pile construction,if abnormal questions occur,construction should be suspended immediately and specific solutions needed to be put forward before continuing construction.
Keywords:unshielded sea area  complicated geological condition  bored pile  steel casing  borehole  construction technology
本文献已被 CNKI 等数据库收录!
点击此处可从《水运工程》浏览原始摘要信息
点击此处可从《水运工程》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号