首页 | 本学科首页   官方微博 | 高级检索  
     检索      

上软下硬地层超深T形地连墙成槽施工难题的处理
引用本文:陈日胜,周翰斌.上软下硬地层超深T形地连墙成槽施工难题的处理[J].水运工程,2011(11):232-236.
作者姓名:陈日胜  周翰斌
作者单位:中交四航局第一工程有限公司,广东广州,510500
基金项目:中交四航局2009年科技研发计划(2009-B-01)
摘    要:埃及塞得东港集装箱码头二期工程的超深T形地下连续墙位于上软下硬且临海水位高的地层中,由于软弱土层深厚且槽孔深度超过60 m,因此成槽技术是施工的关键,需要解决槽壁易坍塌及确保槽孔垂直精度大于1/300这2个重大技 术难题。选择液压抓斗成槽机及旋挖钻机组合作为成槽施工的主要设备,施工中通过采取钻设引导孔、槽壁预加固、改善泥浆性能、保持槽内液面等一系列有效的技术措施,解决了成槽施工的重大技术难题。结果证明:超深T形墙的槽孔垂直精度高,没有塌孔现象,成槽时间较短,成本低,能够保证工程质量,取得了良好的社会效益和经济效益。

关 键 词:超深T形地下连续墙  槽壁预加固  成槽施工  液压抓斗成槽机  

Treatment for trench construction puzzle of super-deep T-shape diaphragm wall in two- layered stratum
CHEN Ri-sheng,ZHOU Han-bin.Treatment for trench construction puzzle of super-deep T-shape diaphragm wall in two- layered stratum[J].Port & Waterway Engineering,2011(11):232-236.
Authors:CHEN Ri-sheng  ZHOU Han-bin
Institution:The First Construction Co., Ltd. of CCCC Fourth Harbor Engineering Co., Ltd., Guangzhou 510500, China
Abstract:Super-deep T-shape diaphragm walls of Port Said East Container Terminal-Phase 2 Marine Works in Egypt are embedded in a two-layered stratum with soft upper and hard lower layers with high water head by sea. Because of more than 60 m depth of groove, the technology of trenching was crucial, and groove walls easy to collapse and its verticality insured more than 1/300 were two of momentous technical puzzles to be solved. Central equipments with hydraulic grab buckets and rotary drilling drivers were selected for the trench construction. In the process of trenching, some effective measures were adopted such as guide wall construction, groove walls advance reinforcement, mud of allocated proportion, liquid level controlling, etc., and momentous technical puzzles of trench construction were solved. Results show that the verticality of super-deep T-shape diaphragm walls is very well without its hole collapse. The trench can be finished with short time, low cost and good quality, and good social and economical benefits are gained.
Keywords:super-deep T-shape diaphragm wall  groove wall advance reinforcement  trench construction  hydraulic grab bucket
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《水运工程》浏览原始摘要信息
点击此处可从《水运工程》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号