LI Ning  LI Guoliang 《隧道建设》2018,38(3):481-493
Lanzhou Chongqing Railway is located in the uplift margin of the Tibetan Plateau, where the geological environment is very complicated and special. Based on numerical analysis and field tests, the physical and mechanical properties, micro structure, and complicated water related stability of the Tertiary sandstone are studied. A comprehensive dewatering system integrating deep surface wells and vacuum light well points in tunnel is used and the construction technique featured with advance reinforcement by horizontal jet grouting for the full face of aquiferous silty fine sand tunnels is invented to solve the problem of the Tertiary quick sand. In addition, the classification method for deformation potentiality in design and dynamic adjustment in construction of tunnels in high geostress soft rock is established, the deformation control technology combining active stress release and passive control according to the deformation mechanism is developed, an automatic real time monitoring system for operation is invented, and a complete technological system of design, construction, and operation management of soft rock tunnels is built. Moreover, the TBM equipment parameter design principles are put forward, the parallel lining and multi stage belt conveyor mucking system is researched, the phased ventilation technology is invented and thus the problem of safe and fast long distance construction by large diameter TBMs is solved. The technological achievements have filled in gaps and facilitated development of the tunnel construction technology.  相似文献   

2.
A sea crossing tunnel is generally large in scale, having a complex site environment, and lack of engineering experience. The success of the project is directly related to the design plan. At present, no metro sea crossing tunnel havd been built in mainland, and the design standard and technology of the sea crossing tunnel are not studied throughly. The key technology of long and large sea crossing metro tunnel design, including construction method selection, cross section design, waterproofing and drainage system design, response to complex environment in sea area, durability design, ventilation and evacuation are analyzd with methods of geological analysis, engineering analogy and comprehensive comparison based on the sea crossing tunnel of Xiamen Rail Transit Line 3. A combination of shield and mining methods is proposed for the geological conditions of different sections. The drainage system of the mining section can be maintained by applying advanced grouting to control displacement. The complex geology of the sea area is considered in the targeted design, including a deep weathering trough, a water rich sand layer, a hard rock and uneven stratum, and the development of solitary rocks. The durability design of the tunnel structure and the limit of the bearing capacity are treated equally to consider safety reserve. The tunnel adopts sectioned longitudinal ventilation and smoke extraction mode, and contains ventilation shafts and civil smoke extraction air shafts on shore to prevent disasters. The conclusions can provide technical support for tunnel scheme decision and reference for similar projects.  相似文献   

3.
In order to guarantee the stability of surrounding rock and support structure of super large span tunnel and realize quantification of support structure design, the optimal excavation contour line shape is obtained based on study of influence of initial ground stress on bearing arch of surrounding rock; a new quantitative design method, in which the surrounding rock is regarded as an arch structure, bolts, cables, shotcrete and lining are designed to satisfy the intensity, rigidity and stability of the arch structure, is presented to design the support structure system. The method has been successfully applied to super large span tunnel of Badaling Great Wall Station on Beijing Zhangjiajie High speed Railway; and the applicable results show that the maximum accumulative settlement of crown top of large span section is only 17.3 mm, and the relative subsidence of crown top is only 0.09%, which can meet safety requirements.  相似文献   

4.
The author gives an overview of the development of tunnels and underground engineering in China in the past two years, including railway tunnel, high speed railway tunnel, highway tunnel, metro tunnel, hydraulic tunnel and utility tunnel, and introduces some key and representative railway, highway and municipal tunnels projects, i.e. Muzhailing Tunnel on Lanzhou Chongqing Railway, Dangjinshan Tunnel on Dunhuang Golmud Railway, immersed tunnel of Hong Kong Zhuhai Macao Bridge, China Laos Railway Tunnel, Gaoligongshan Tunnel on Dali Ruili Railway, Yuelongmen Tunnel on Chengdu Lanzhou Railway, Tianshan Shengli Tunnel on Urumchi Yuli County High speed Railway, Shenzhen Zhongshan Passage, Su′ai Tunnel in Shantou, Ka Shuang Tunnel of Ertix River Water Diversion Project, Qianhai underground integrated hub in Shenzhen and underground integrated structure of Optics Valley Square in Wuhan. The author also introduces the development and progress in the fields of engineering investigation technology, BIM technology, mechanized and intelligent tunnel construction technology, shield/TBM manufacturing and remanufacturing technology, offshore immersed tube tunnel construction technology, non circular shield tunnel construction technology, tunnel big data platform construction technology, etc. According to the operation of series national strategies and planning such as Sichuan Tibet Railway, coordinated development of Beijing, Tianjin and Hebei, the Yangtze Economic belt, and the Guangdong Hong Kong Macao Greater Bay Area, following technical demands are proposed, namely, sea crossing tunnels, construction of complex and long distance tunnels, environmental protection technology for tunnel construction in ecologically vulnerable areas, development of large scale urban underground complexes, research and development of new materials in alpine environment, intelligent diagnosis of tunnel diseases and rapid repairs, intelligent disaster prevention of ultra long complicated tunnels and underground engineering, etc. Some thoughts and suggestions are put forward in two aspects of engineering construction management mode and mechanization supporting in combination with the development status of the industry.  相似文献   

5.
In recent years, with the help of good national policy support, the design, manufacturing and construction technology for tunnel boring machine (TBM) in China have been greatly improved; but compared with foreign relatively proven technology, there is still a certain gap for domestic technology development and engineering application. Based on the situation analysis of research and application of TBM in China and abroad, the research work for TBM design is carried out according to the complex geological conditions of Gaoligongshan Tunnel on Dali Ruili Railway as follows. (1) The prototype disc cutter rock breaking and scaled disc cutter wearing experiment are carried out to provide reference for adaptable design of TBM cutterhead and key parameter calculation. (2) The TBM design scheme is discussed from the aspects of high efficiency rock breaking of cutters and cutterhead, TBM over excavation, integrated support system, etc. (3) Two kinds of advanced geological prediction technology, i.e. HSP method and RTP method, are researched. The study results can provide reference for design and manufacture of TBM with high adaptability in complex geology and construction application in Gaoligongshan Tunnel.  相似文献   

6.
The total length of the 2nd stage water transfer project in the northern area of Xinjiang of China is 540 km. The project consists of three tunnels, namely Xi Er (XE) Tunnel, Ka Shuang (KS) Tunnel and Shuang San (SS)〖HJ6.5mm〗 Tunnel, with lengths of 139.04 km, 283.27 km and 92.15 km respectively. All of these three tunnels have deep cover and are super long tunnels, and 95.6% of the total length of these three tunnels is constructed by TBMs. KS Tunnel is the longest water tunnel built or under construction in the world. In the paper, the trial TBM boring scheme and schedule of the water transfer project are introduced; the geological conditions revealed are statistically analyzed; and main project difficulties, i.e. durability of key equipment in long distance driving, passing through fault and fracture zones, water inrush, single head ventilation and transportation in long distance tunneling, anti slope drainage, and rock breaking efficiency and boring efficiency, are put forward. The adaptability of the TBMs used is analyzed from the aspects of adaptability to different surrounding rocks, adaptability to bad geological conditions and countermeasures, long distance ventilation and belt conveyor mucking and countermeasures, and TBM boring stability (such as equipment availability, boring time proportion, system malfunction and operation time). The following conclusions are obtained: (1) Accurate geological survey is the precondition of efficient tunneling. (2) The open type TBM can better adapt to Grade Ⅱ and Ⅲ of surrounding rocks, jointed and fractured zones and small faults; the adaptability of the TBMs used to the large scale fault fracture zones and water rich strata in this project is poor, and it needs to be improved in aspects of TBM equipment, supporting and construction technology. (3) The average availability of the TBM equipment in the trial boring stage is 89.9%, however, the malfunction rate of some ancillary equipment is high, particularly oil leakages occur to the main bearing seals; in order to achieve long distance tunneling, it is necessary to further improve the reliability and durability of the TBM equipment. (4) The average net boring efficiency in the trial boring stage is 296%, and TBM1 in Section Ⅱ of SS Tunnel achieves up to 45.2 % net boring efficiency; and highest monthly progress rate is 1 280 m, which created the highest record of the open type TBM boring in China. (5) TBM need to make great efforts to achieve 90% of the equipment system′s availability and over 40% of the tunneling efficiency.  相似文献   

7.
NIU Bin  WANG Qi  GUO Ting 《隧道建设》2019,39(4):661-668
The design and flood flowing safety measures of the metro station in the flood district, such as scour protection, flood control, collision prevention and floating resistance, are studied based on the flood control evaluation on the Dongzhuang Station of the Shijiazhuang Metro Line 1 Project (Phase Ⅱ). Then feasible design measures are put forward to meet the requirements of flood control evaluation during different flood return periods. The design scope for main works includes: increasing the burial depth of the station, using the retaining piles as the anti floating piles, and adopting the heightened anti flooding retaining wall and anti flooding baffle. Additionally, the civil air defense door is also used as the flood gate in case of the unelevated ground at the entrance/exit in auxiliary works. Finally, the base slab at the entrance/exit is lower than the area below the maximum scouring line, the counterweight is backfilled in the void space, and the integral rigidity of the auxiliary structure is enhanced.  相似文献   

8.
TAN Shunhui  SUN Heng 《隧道建设》2019,39(7):1073-1082
By analyzing the application cases of super large diameter shield machine in the world and taking China Shantou Gulf Tunnel and Shenzhen Chunfeng Tunnel construction for examples, the problems encountered in the research and development and construction are proposed and the key technologies to solve a series of problems, such as cutterhead maintenance and cutter changing technology under high soil and water pressure, boring in long fractured zone, are explored. More specifically, the technologies mainly involve cutterhead design, atmospheric cutter changing, main drive with telescopic and swinging function, reliable sealing system, anti blockage technique by applying double crushers, which are of great significance to the development and application of super large diameter shield machine.  相似文献   