大跨混凝土斜拉桥拉索施工期的可靠度分析
引用本文:刘扬,张建仁,余志武. 大跨混凝土斜拉桥拉索施工期的可靠度分析[J]. 中国公路学报, 2007, 20(3): 41-47
作者姓名:刘扬  张建仁  余志武
作者单位:1. 长沙理工大学,桥梁与结构工程学院,湖南,长沙,410076;中南大学,土木建筑学院,湖南,长沙,410075
2. 长沙理工大学,桥梁与结构工程学院,湖南,长沙,410076
3. 中南大学,土木建筑学院,湖南,长沙,410075
基金项目:国家自然科学基金;交通部交通应用基础研究基金
摘    要:从结构可靠度理论出发,采用极值分布方法直接推导建立了斜拉索的强度概率模型,通过现场试验得到了钢绞线式斜拉索的索力均匀性指标,分析了影响施工期索力的主要设计变量的概率特征,在此基础上提出施工期斜拉索的可靠指标计算方法;进而分析施工阶段拉索可靠水平的变化规律,从而基于结构可靠度理论提出施工期斜拉索的安全性评价方法,并结合大跨混凝土斜拉桥实际工程背景验证了这一方法的有效性。计算结果表明:施工期斜拉索的可靠指标小于运营期;研究成果对于评价混凝土斜拉桥施工期的结构整体性能和安全程度具有参考价值。

关 键 词:桥梁工程  斜拉索  极值分布方法  可靠度
文章编号:1001-7372(2007)03-0041-07
收稿时间:2006-09-21
修稿时间:2006-09-21

Reliability Analysis of Stay Cables for Long-span Concrete Cable-stayed Bridges During Construction
LIU Yang,ZHANG Jian-ren,YU Zhi-wu. Reliability Analysis of Stay Cables for Long-span Concrete Cable-stayed Bridges During Construction[J]. China Journal of Highway and Transport, 2007, 20(3): 41-47
Authors:LIU Yang  ZHANG Jian-ren  YU Zhi-wu
Affiliation:1. School of Bridge and Structural Engineering, Changsha University of Science and Technology, Changsha 410076, Hunan, China; 2. School of Civil Engineering and Architecture, Central South University, Changsha 410075, Hunan, China
Abstract:Based on the theory of structure reliability, an extreme-value-distribution method was proposed for establishing the probabilistic model for stay cable strength directly. The uniformity indexes of the steel wire strand force of stay cable were studied through experiment in the field. The probabilistic characteristic of main design variables influencing cable force was also analyzed. Then, index reliability calculation method of stay cable during construction was put forward which was used to analyze variation rules of cable reliability level during construction. Based on the method, safety evaluation method of stay cable during construction was put forward. A longspan concrete cable-stayed bridge was selected to show the efficiency and accuracy of the proposed algorithm. The results show that reliability index of stay cable during construction is usually lower than that during running. The study result can provide reference for structural whole performance and safety degree of concrete cable-stayed bridges during construction.
Keywords:bridge engineering   stay cable   extreme-value-distribution method   reliability