盾构地铁隧道近接施工及旁穿全装配高层壁板居民楼施工技术
引用本文:蔡永立,冯晓科,曾德光,陈英盈.盾构地铁隧道近接施工及旁穿全装配高层壁板居民楼施工技术[J].隧道建设,2008,28(3):314-317.
作者姓名:蔡永立  冯晓科  曾德光  陈英盈
作者单位:1. 北京住总市政工程有限责任公司,北京,100029
2. 北京城建设计研究总院,北京,100037
摘    要:介绍了北京地铁10号线麦子店—三元桥站—亮马河站区间(左右线净距离仅为1.7~3m,平行穿越长度为235m)及旁穿12层全装配壁板居民楼(与其基础水平净距离3.7~5m左右,垂直距离为11.7m)的施工总体思路和具体做法。其中首次提出了综合松散系数K的理论计算公式并给出了K的实测方法。在合理使用铰接装置和超挖刀、控制盾构推力、及时复拧管片螺栓等常规措施的基础上提出了盾构曲线段施工的两个新措施:一是考虑到盾构机的惯性,曲线段提前3~5m开始转弯,并提前3~5m结束转弯;二是考虑到曲线段盾构在管片脱出盾尾后产生扭转而非平移,对盾构进行预偏转。

关 键 词:土压平衡盾构  近接施工  曲线段施工  旁穿全装配壁板居民楼  十字钢支撑  沉降控制
收稿时间:2008-03-18
修稿时间:2008-05-16

Construction Technology for Small-spaced Twin-tube Shield-bored Tunnels Crossing underneath close to High-rise Assembled Residential Buildings
CAI Yongli,Feng Xiaoke,Zeng Deguang,Chen Yingying.Construction Technology for Small-spaced Twin-tube Shield-bored Tunnels Crossing underneath close to High-rise Assembled Residential Buildings[J].Tunnel Construction,2008,28(3):314-317.
Authors:CAI Yongli  Feng Xiaoke  Zeng Deguang  Chen Yingying
Institution:1. Municipal Engineering Co., Ltd., Beijing Housing Group, Beijing 100029, China| 2. Beijing urban engineering design and research institute Co.,Ltd.|Beijing 100037,China
Abstract:Maizidian Sanyuanqiao Liangmahe shield bored tunnel on Line 10 of Beijing Metro consists of twin tubes, which go parallel for 235m with only 1.7~3m net spacing. The tunnel crosses underneath close to a 12 storey assembled residential building, with the horizontal net distance to the building foundations being 3.7~5m and the vertical net distance to the building foundations being 11.7m. The construction of the shield bored tunnel is presented in the paper. The theoretical calculation equations and the measurement methods for the comprehensive looseness coefficient “K” are provided. In additional to the conventional construction measures, such as proper use of the articulations and over cutters, proper control of the thrust forces of the shields and timely re tightening of the segment bolts, two items of new countermeasures are proposed for the construction of the curved sections of the shield bored tunnels. The two items of new countermeasures include: 1) Due to the inertia of the shields, the shields start to bore on curved sections 3~5m ahead of the schedule and stop the boring on the curved sections 3~5m ahead of the schedule; 2) Due to the rotation of the shields on the curved sections when the segment rings are released, rotation rectifying measures are taken in advance.
Keywords:earth pressure balanced shield  tunnel boring close to existing structure  tunnel boring on curved section  tunnel boring underneath close to assembled residential building  cross shaped steel support  settlement control