九江长江公路大桥北塔下横梁施工方案研究
引用本文:贺鹏,常英,张延河,张家元.九江长江公路大桥北塔下横梁施工方案研究[J].世界桥梁,2012,40(4):64-68.
作者姓名:贺鹏  常英  张延河  张家元
作者单位:1. 湖北省交通规划设计院,湖北武汉,430051
2. 中交第二航务工程局有限公司,湖北武汉,430012
摘    要:九江长江公路大桥主桥采用(70+75+84)m+818 m+(233.5+124.5)m双塔不对称混合梁斜拉桥,H形桥塔塔肢间设上、中、下3道横梁.为确定该桥北塔下横梁施工方案,对同步施工方案、异步施工方案、异步施工+主动横撑方案进行分析.结果表明:异步施工+主动横撑方案结构受力合理、施工工期短、施工风险小,确定为下横梁最终施工方案.经优化,主动横撑采用2根Φ1200 mm×12 mm的螺旋焊管制作,每根施加2000 kN 水平推力,在下横梁第一层混凝土强度达到90%之后,施加第一批横向预应力前撤掉水平推力;采取增加塔柱混凝土凿毛厚度、加强局部振捣的方法,保证新老混凝土结合面混凝土的施工质量.

关 键 词:斜拉桥  桥塔  下横梁  同步施工  异步施工  主动横撑  方案比选

Construction Scheme Study of Lower Cross Beam of North Pylon of Jiujiang Changjiang River Highway Bridge
HE Peng , CHANG Ying , ZHANG Yan-he , ZHANG Jia-yuan.Construction Scheme Study of Lower Cross Beam of North Pylon of Jiujiang Changjiang River Highway Bridge[J].World Bridges,2012,40(4):64-68.
Authors:HE Peng  CHANG Ying  ZHANG Yan-he  ZHANG Jia-yuan
Institution:1(1.Hubei Provincial Transport Planning and Design Institute,Wuhan 430051,China; 2.CCCC Second Harbor Engineering Co.,Ltd.,Wuhan 430012,China)
Abstract:The main bridge of Jiujiang Changjiang River Highway Bridge is a two-pylon asymmetrical hybrid girder cable-stayed bridge with span arrangement of(70+75+84) m+818 m+(233.5+124.5) m.The H-shaped pylon of the bridge is equipped with three cross beams: the upper,the intermediate and the lower cross beams.To determine the construction scheme for the lower cross beam of the north pylon,the schemes of synchronous construction,asynchronous construction and asynchronous construction plus active cross brace are analysed.The results of the analysis indicate that the scheme of asynchronous construction plus active cross brace prevails over the other two schemes,it can cut down construction time and reduce the construction risk,and the addition of active cross brace improves the stress condition at the base of the bridge pylon,which is finally determined as the construction scheme for the lower cross beam.After optimization,the active cross brace is made from 2 spiral welded pipes of 1 200 mm×12 mm in diameter,and each pipe is applied with a horizontal push of 2 000 kN.When the intensity of the first layer concrete of the Lower cross beam reached 90%,the horizontal push was removed,then,the tensioning of the prestress of the first batch of cross beams began.To guarantee the construction quality of the concrete at the old and new concrete interface,the method of increasing the chiseling thickness and intensing local vibrating of the pylon leg concrete was adopted.
Keywords:cable-stayed bridge  pylon  lower cross beam  synchronous construction  asynchronous construction  active cross brace  scheme comparison and selection