某高速铁路试验段路基沉降实测及有限元分析
引用本文:李波,冷景岩.某高速铁路试验段路基沉降实测及有限元分析[J].路基工程,2013,0(6):35-37.
作者姓名:李波  冷景岩
作者单位:铁道第三勘察设计院集团有限公司,天津 300251
基金项目:铁道部科技研究开发计划(2010G003-F)
摘    要:基于某高速铁路试验段路基沉降的实测,建立有限元模型进行模拟,得出了和实测拟合较好的计算结果。实测及有限元分析表明:路基填筑完成后预压三个月,沉降仍有一定发展趋势,不足以消除后期沉降的影响,路基在填筑后沉降发展需要很长时间才能完成。

关 键 词:高速铁路    路基沉降    实测    有限元
收稿时间:2019-11-09

Actual Measurement and FEM Analysis on Subgrade Settlement in the Testing Section of A High-speed Railway
Authors:LI Bo  LENG Jingyan
Institution:(The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251, China)
Abstract:Subgrade settlement was simulated with a finite element model established on the basis of the data measured in the testing section of a high-speed railway, then a result fitted the measured result was obtained. The result of the actual measurement and the FEM analysis thereof show that through 3-months preloading after the subgrade filling, the settlement still develops and the effect of the post-construction settlement is not eliminated completely; hence, it takes a long time to finish the development of subgrade settlement after construction.
Keywords:high-speed railway  subgrade settlement  actual measurement  finite element