某高速铁路试验段路基沉降实测及有限元分析 |
| |
引用本文: | 李波,冷景岩.某高速铁路试验段路基沉降实测及有限元分析[J].路基工程,2013,0(6):35-37. |
| |
作者姓名: | 李波 冷景岩 |
| |
作者单位: | 铁道第三勘察设计院集团有限公司,天津 300251 |
| |
基金项目: | 铁道部科技研究开发计划(2010G003-F) |
| |
摘 要: | 基于某高速铁路试验段路基沉降的实测,建立有限元模型进行模拟,得出了和实测拟合较好的计算结果。实测及有限元分析表明:路基填筑完成后预压三个月,沉降仍有一定发展趋势,不足以消除后期沉降的影响,路基在填筑后沉降发展需要很长时间才能完成。
|
关 键 词: | 高速铁路 路基沉降 实测 有限元 |
收稿时间: | 2019-11-09 |
Actual Measurement and FEM Analysis on Subgrade Settlement in the Testing Section of A High-speed Railway |
| |
Authors: | LI Bo LENG Jingyan |
| |
Institution: | (The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251, China) |
| |
Abstract: | Subgrade settlement was simulated with a finite element model established on the basis of the data measured in the testing section of a high-speed railway, then a result fitted the measured result was obtained. The result of the actual measurement and the FEM analysis thereof show that through 3-months preloading after the subgrade filling, the settlement still develops and the effect of the post-construction settlement is not eliminated completely; hence, it takes a long time to finish the development of subgrade settlement after construction. |
| |
Keywords: | high-speed railway subgrade settlement actual measurement finite element |