浅析现浇箱梁满堂支架搭设施工方案
引用本文:陈荣凯. 浅析现浇箱梁满堂支架搭设施工方案[J]. 筑路机械与施工机械化, 2012, 29(1): 72-74
作者姓名:陈荣凯
作者单位:新疆北新路桥建设股份有限公司,新疆乌鲁木齐,830011
摘    要:为进一步探讨满堂支架法的搭设施工工艺和力学计算特点,结合重庆沿江高速W5标段双河口互通B匝道桥现浇箱梁满堂支架搭设施工的实例,以B3联为研究对象,对满堂支架搭设方案及其力学验算过程进行了分析,得出了满堂支架搭设的一般工艺和验算方法.

关 键 词:现浇箱梁  满堂支架  支架搭设  力学计算

Discussion on Support Construction Method of Cast-in-place Box Beam
CHEN Rong-kai. Discussion on Support Construction Method of Cast-in-place Box Beam[J]. Road Machinery & Construction Mechanization, 2012, 29(1): 72-74
Authors:CHEN Rong-kai
Affiliation:CHEN Rong-kai Xinjiang Beixin Road & Bridge Construction Co. Ltd., Urumqi 830011, Xinjiang, China
Abstract:For further discussion the erection technology and characteristics of mechanical calculation, com- bined with the support construction method of cast-in-place box beam of the bridge at alternative ramp B of dou- ble estuary in W5 section of expressway along Yangtze River in Chongqing, the erection scheme and the me- chanical calculation process of the support in B3 section were analyzed. The general technology and calculation method of support erection were concluded.
Keywords:cast-in-place box beam  support construction method  support erection  mechanical calculation