双圆盾构隧道下穿原水管渠的施工监测
引用本文:徐敏.双圆盾构隧道下穿原水管渠的施工监测[J].城市轨道交通研究,2006,9(8):67-68.
作者姓名:徐敏
作者单位:上海市原水股份有限公司,200080,上海
摘    要:作为国内首次采用双圆盾构下穿重要原水管渠工程,通过对其施工过程进行跟踪监测,得出双圆盾构隧道下穿原水管渠施工时的管渠变形规律,为以后类似工程提供了有价值的数据参考。

关 键 词:双圆盾构  施工监测  地基变形
收稿时间:2006-06-19
修稿时间:2006年6月19日

Construction Monitoring of Raw Water Culvert Deformation
Xu Min.Construction Monitoring of Raw Water Culvert Deformation[J].Urban Mass Transit,2006,9(8):67-68.
Authors:Xu Min
Institution:Shanghai Yuanshui Co., Ltd,, 200080, Shanghai, China
Abstract:Being the first case of double circle shielding under pipe culvert in China,the whole course of the construction of Shanghai rail transit Line 6 is monitored.According to the regular patterns of pipe culvert deformation caused by double circle shield construction,the author argues that the construction is successfully carried out,which can serve as a reference for the same projects.
Keywords:double circle shield  construction monitoring  foundation deformation