首页 | 本学科首页   官方微博 | 高级检索  
     检索      

采用柱状锤强夯法解决重力式码头背后回填地基沉降问题
引用本文:朱劲松.采用柱状锤强夯法解决重力式码头背后回填地基沉降问题[J].港工技术,2014(4):69-71.
作者姓名:朱劲松
作者单位:中交一航局第五工程有限公司,河北秦皇岛066002
摘    要:重力式码头背后回填地基暂无较好的处理工艺,导致该区域后期沉降普遍较大,影响码头观感质量,严重时影响码头使用功能。本文结合锦州港第二港池集装箱码头二期工程,介绍采用柱状锤强夯法处理重力式码头背后回填地基的施工工艺及效果,希望能为类似工程的施工提供借鉴经验。

关 键 词:柱状锤  强夯  沉降处理

Application of Pillar-hammer Tamping Method in Sedimentation Treatment of Backfill Foundation in Rear of Gravity Wharf
Zhu Jinsong.Application of Pillar-hammer Tamping Method in Sedimentation Treatment of Backfill Foundation in Rear of Gravity Wharf[J].Port Engineering Technology,2014(4):69-71.
Authors:Zhu Jinsong
Institution:Zhu Jinsong (No.$ Engineering Co., Ltd. of CCCC First Harbor Engineering Co., Ltd., Qin Huangdao He Bei 066002, China)
Abstract:Due to the lack of treating technology process for the backfill foundation in the rear of gravity wharf, large post-construction settlement of the region occurs, which may influence the appearance quality, even the functions of the wharf. Based on Jinzhou Port No.2 Basin Container Terminal Phase-2 project, the construction technologies and effect of pillar-hammer tamping method is indicated, which will be used to treat the backfill foundation in the rear of gravity wharf. The research results will provide references for similar project.
Keywords:pillar-hammer  tamping  sedimentation treatment