独塔斜拉桥换索过程计算分析研究
引用本文:姬然,郑凯锋,庞竞拓.独塔斜拉桥换索过程计算分析研究[J].广东公路交通,2013(5):13-16,26.
作者姓名:姬然  郑凯锋  庞竞拓
作者单位:西南交通大学土木工程学院,成都610031
摘    要:建立独塔斜拉桥设计方案的全桥有限元模型,综合考虑主梁内力对成桥索力进行优化;计算施工阶段拉索初拉力.分析逐一卸除各拉索工况下拉索力和应力的变化及其极值;计算各换索工况下主梁和桥塔的应力变化,分析换索过程中桥梁能否正常运营.还对各换索工况下主梁竖向位移进行了分析.

关 键 词:独塔斜拉桥  有限元分析  换索过程分析

Analysis on Cable Replacement for a Single Tower Cable-stayed Bridge
JI Ran,ZHENG Kaifeng,PANG Jingtuo.Analysis on Cable Replacement for a Single Tower Cable-stayed Bridge[J].Guangdong Highway Communications,2013(5):13-16,26.
Authors:JI Ran  ZHENG Kaifeng  PANG Jingtuo
Institution:(School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, China)
Abstract:A finite element model of a single tower cable-stayed bridge was established. An optimization of initial stay-cable force was conducted based on the force of steel box girder; initial stay-cable forces considered con- struction stages were also calculated in this paper. Stay-cable forces and stresses in each cable replacement con- dition were calculated. Extreme values and corresponding variation were analyzed. Stress of box girders and tow- ers were also calculated in order to determine whether limitation of traffic is necessary. At last, vertical displace- ments of box girder i~ each cable replacement condition were analyzed.
Keywords:single tower cable-stayed bridge  finite element analysis  cable replacement analysis