新建南通至启东铁路施工总工期方案比选
引用本文:侯鹏飞.新建南通至启东铁路施工总工期方案比选[J].铁路工程造价管理,2011,26(2):21-24.
作者姓名:侯鹏飞
作者单位:中铁上海设计院集团有限公司,上海,200438
摘    要:施工组织设计是指导工程建设的重要技术经济文件,合理确定施工组织方案和总工期是施工组织设计的核心,也是确定工程投资和合理安排工程建设的重要条件。此文根据铁建设2009]226号《铁路工程施工组织设计指南》,结合新建铁路宁启线南通至启东工程实践,分析研究主要施工组织方案及施工总工期方案。

关 键 词:宁启铁路  总工期  方案比选  施工组织  控制工程

Comparison and Selection of Total Time Limit Schemes of the New Construction of the Nantong- Qidong Railway
Hou Pengfei.Comparison and Selection of Total Time Limit Schemes of the New Construction of the Nantong- Qidong Railway[J].Railway Engineering Cost Management,2011,26(2):21-24.
Authors:Hou Pengfei
Abstract:The construction organization design is the important technological and economic document which guides the engineering construction.It is key to the construction organization design as well as important for the project investment and construction arrangement to appropriately determine the construction organizational scheme and the total time limit.In terms of the guide of construction organization design(2009),this paper studies the construction organization scheme and the total time limit scheme of the new...
Keywords:Nantong-Qidong railway  total time limit  scheme comparison  construction organization  control engineering  