振动沉管法CFG桩的施工技术
引用本文:刘绍舜,罗贤武,房铁柱,彭学良.振动沉管法CFG桩的施工技术[J].筑路机械与施工机械化,2007,24(10):51-53.
作者姓名:刘绍舜  罗贤武  房铁柱  彭学良
作者单位:中国葛洲坝集团公司,湖北,宜昌,443002
摘    要:从材料组成特点、受力特点、施工特点及施工周期等4个方面简述了振动沉管法CFG桩的特点,并结合汉洪高速公路的施工实例,从原材料、混凝土配合比和施工流程等方面介绍了CFG桩的施工工艺,最后总结了施工中常见的几个问题及质量控制措施。

关 键 词:CFG桩  施工工艺  问题  质量控制措施
文章编号:1000-033X(2007)10-0051-03
修稿时间:2006-02-21

Construction of CFG Pile for Vibratory Immersed Tunneling Method
LIU Shao-shun,LUO Xian-wu,FANG Tie-zhu,PENG Xue-liang.Construction of CFG Pile for Vibratory Immersed Tunneling Method[J].Road Machinery & Construction Mechanization,2007,24(10):51-53.
Authors:LIU Shao-shun  LUO Xian-wu  FANG Tie-zhu  PENG Xue-liang
Institution:China Gezhouba Group Co., Yichang 443002, Hubei, China
Abstract:The CFG pile characteristics of vibratory immersed tunneling method are discussed from aspects such as materials, stress features, construction and construction period. The construction technology of CFG pile is introduced from raw materials, concrete gradation and construction process according to the construction of Hanhong Expressway construction. Several commonly encountered questions and quality control measures are summarized.
Keywords:CFG pile  construction technology  question  quality control measure