大埋深裂隙岩层中土压平衡盾构下穿水道施工安全性分析
引用本文:吴文彪,李锦平,林辉,封坤,王闯.大埋深裂隙岩层中土压平衡盾构下穿水道施工安全性分析[J].铁道建筑,2019(8):81-83,107.
作者姓名:吴文彪  李锦平  林辉  封坤  王闯
作者单位:粤水电轨道交通建设有限公司;广东珠三角城际轨道交通有限公司;西南交通大学交通隧道工程教育部重点实验室
基金项目:国家重点研发计划(2016YFC0802202);国家自然科学基金(51578462)
摘    要:广州-佛山环线沙堤隧道在大埋深裂隙岩层中采用土压平衡盾构法下穿佛山水道,采用FLAC 3D软件建立流固耦合数值模型,分析隧道下穿水道施工安全性。研究结果表明:下穿施工时引起地下水渗流,其中横断面方向影响范围约为隧道洞径的3. 6倍,纵断面方向影响范围约为隧道洞径的2. 4倍;在一定支护压力下开挖面具有一定的自稳能力,支护压力较小时在水压力的作用下开挖面易发生失稳破坏;在大埋深裂隙岩层中采用土压平衡盾构法施工时,应保证土仓的止水能力。

关 键 词:城际铁路隧道  水下施工安全性  数值计算  土压平衡盾构  大埋深裂隙岩层

Construction Safety Analysis of Earth Pressure Balanced Shield Tunnel Under-crossing Waterway in Deep Buried Fractured Rock Stratum
WU Wenbiao,LI Jinping,LIN Hui,FENG Kun,WANG Chuang.Construction Safety Analysis of Earth Pressure Balanced Shield Tunnel Under-crossing Waterway in Deep Buried Fractured Rock Stratum[J].Railway Engineering,2019(8):81-83,107.
Authors:WU Wenbiao  LI Jinping  LIN Hui  FENG Kun  WANG Chuang
Institution:(YSD Rail Transit Construction Co.Ltd.,Guangzhou Guangdong 510610,China;Guangdong Pearl River Delta IntercityRailway Co.Ltd.,Guangzhou Guangdong 510000,China;Key Laboratory of Transportation Tunnel Engineering,Ministry of Education,Southwest Jiaotong University,Chengdu Sichuan 610031,China)
Abstract:The Shadi tunnel of Guangzhou-Foshan loop line under-crosses the Foshan waterway by the earth pressure balanced shield tunneling method in the deep buried fractured rock stratum.FLAC 3D software was used to establish a f luid-solid coupling numerical model to analyze the construction safety of tunnel under-crossing the waterway.Research results show that groundwater seepage is caused by under-crossing construction,the inf luence range of cross-section direction is about 3.6 times the tunnel diameter,and the inf luence range of longitudinal section direction is about 2.4 times the tunnel diameter.The excavation face has certain self-stabilization ability under certain support pressure,the excavation face is prone to destabilization under the action of water pressure when the support pressure is low.When the earth pressure balanced shield tunneling method is used in the deep buried fractured rock stratum,the sealing capacity of the earth silo should be guaranteed.
Keywords:Intercity railway tunnel  Safety of underwater construction  Numerical calculation  Earth pressure balanced shield tunnel  Deep buried fractured rock stratum