大准增二线丹洲营车站施工过渡方案研究
引用本文:梁婷.大准增二线丹洲营车站施工过渡方案研究[J].铁道建筑技术,2014(8):18-21.
作者姓名:梁婷
作者单位:中铁第五勘察设计院集团有限公司,北京102600
摘    要:大准增二线丹洲营车站改造的施工过渡重难点是既有线抬道和16号中桥的新建,介绍了制定施工过渡方案的主要原则,提出具体的施工过渡方案并进行分析比较,推荐采用便线位于既有线左侧方案。

关 键 词:大准铁路  丹洲营车站  施工过渡  方案比选

Study on Transition Scheme for Danzhouying Station in the Construction of the Second Datong-Junger Line
Liang Ting.Study on Transition Scheme for Danzhouying Station in the Construction of the Second Datong-Junger Line[J].Railway Construction Technology,2014(8):18-21.
Authors:Liang Ting
Institution:Liang Ting (China Railway Fifth Survey and Design Institute Group Co. Ltd. , Beijing 102600, China)
Abstract:The key and difficulty of Danzhouying station reconstructing transition is the existing line lifting and No.16 bridge construction.The paper introduced the main principles of establishing construction transition program,put forward the detailed construction transition program.After comparison and analysis,the program of transiting line on the left of the existing line is recommended.
Keywords:Datong-Junger railway  Danzhouying station  construction transition  scheme comparison