西安地铁北客站降水施工技术
引用本文:但晓华.西安地铁北客站降水施工技术[J].铁道建筑技术,2010(2):75-79.
作者姓名:但晓华
作者单位:中铁十八局集团第三工程有限公司,河北涿州,072750
摘    要:西安北客站主体明挖基坑标准段深19.2 m。本站场区地质上层为素填土和黄土状土,下层为沙层,沙层自稳性差,因此基坑施工中确保围护结构稳定性是难点。该工程采用了基坑降水方案,对降水井的设计、计算和施工进行了详细阐述。

关 键 词:地铁车站  降水井  施工技术

Dewatering Construction Technology in North Station of Xi'an Subway
Dan Xiaohua.Dewatering Construction Technology in North Station of Xi'an Subway[J].Railway Construction Technology,2010(2):75-79.
Authors:Dan Xiaohua
Institution:Dan Xiaohua(China Railway 18th Bureau Group Co.Ltd.,Zhuozhou 072750,China)
Abstract:The standard section of open excavated foundation pit in Xi'an North Station main body is 19.2 m in depth.The upper layer of this station is plain fill and loess-like soil,and its lower layer is sand.As the sand layer has a weak stability,ensuring the stability of the surrounding structure is a difficulty in the foundation pit construction.This project adopts the foundation pit dewatering scheme,and this paper elaborates in detail the design,calculation and construction of the dewatering well.
Keywords:subway station  dewatering well  construction technology  